PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 27/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120975 has been updated at 0115 hrs to the following:
[1.] From 1400 hrs 27/11/2024 to 1430 hrs 27/11/2024.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 1052 MW.
[2.] From 1900 hrs 27/11/2024 to 2000 hrs 27/11/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 973 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120989 has been updated at 0100 hrs 27/11/2024 to the following:
[2.] From 0830 hrs 29/11/2024 to 1130 hrs 29/11/2024.
The forecast capacity reserve requirement is 1650 MW.
The minimum capacity reserve available is 1467 MW.
[3.] From 1330 hrs 29/11/2024 to 1900 hrs 29/11/2024.
The forecast capacity reserve requirement is 1487 MW.
The minimum capacity reserve available is 700 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120988 has been updated at 0100 hrs 27/11/2024 to the following:
[1.] From 1200 hrs 28/11/2024 to 2130 hrs 28/11/2024.
The forecast capacity reserve requirement is 1367 MW.
The minimum capacity reserve available is 489 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period[s]:
[1.] From 1700 hrs 28/11/2024 to 1800 hrs 28/11/2024.
The forecast capacity reserve requirement is 776 MW.
The minimum capacity reserve available is 728 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Non-credible contingency event - NSW region - 26/11/2024
Non-credible contingency event - NSW region - 26/11/2024
At 1637 hrs Uranquinty Unit 12 tripped and at 1639 hrs Uranquinty Units 11 and 13 tripped.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 28/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120972 is cancelled at 16:50 hrs 26/11/2024.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120981 has been updated at 1550 hrs to the following:
[1.] From 1630 hrs 26/11/2024 to 1930 hrs 26/11/2024.
The forecast capacity reserve requirement is 1380 MW.
The minimum capacity reserve available is 989 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/11/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 120984 is cancelled at 1545 hrs 26/11/2024.
Manager NEM Real Time Operations
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 121002
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 26/11/2024
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 2330 hrs 26/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 28/11/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations