124231NON-CONFORMANCE06/02/2025 04:31:43 AM

NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 6 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 06/02/2025 01:25 to 06/02/2025 04:30
Amount: -44 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
124229NON-CONFORMANCE06/02/2025 12:25:20 AM

NON-CONFORMANCE Region NSW1 Thursday, 6 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 5 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 05/02/2025 23:15 to 06/02/2025 00:25
Amount: -20 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
124225RESERVE NOTICE05/02/2025 10:32:28 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124191 has been updated to the following:

[1.] From 1600 hrs 06/02/2025 to 1730 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 887 MW.

[2.] From 1930 hrs 06/02/2025 to 2030 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1148 MW.


Manager NEM Real Time Operations
     
124191RESERVE NOTICE05/02/2025 04:42:30 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124157 has been updated to the following:

[1.] From 1730 hrs 06/02/2025 to 1900 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1182 MW.


Manager NEM Real Time Operations
     
124190MARKET SYSTEMS05/02/2025 04:23:24 PM

CHG0100111 | Pre-Production | Pre-Prod eMDM February Maintenance Release

Change Number: CHG0100111

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MDM - Meter Data Management_PreProd

Change Title: Pre-Prod eMDM February Maintenance Release

Change Start Date & Time: 11/02/2025 13:00:00 AEST
Change End Date & Time: 11/02/2025 17:00:00 AEST
Outage Start Date & Time: 11/02/2025 13:00:00 AEST
Outage End Date & Time: 11/02/2025 15:00:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
124184RESERVE NOTICE05/02/2025 04:29:44 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124093 has been updated at 1500 hrs 05/02/2025 to the following:

1. From 1600 hrs to 1630 hrs 07/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1119 MW.

2. From 1900 hrs to 1930 hrs 07/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1306 MW.

AEMO Operations
     
124180GENERAL NOTICE05/02/2025 03:16:32 PM

Update - Vulnerable lines in TAS region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in TAS region
Refer to AEMO Electricity Market Notice 124044
At 1410 hrs 03/02/2025 the Farrell - Reece No.1 and No.2 220 kV lines lines tripped.
The cause of the trip was identified as due to lightning.
In accordance with SO_OP_3715, AEMO now considers the Farrell - Reece No.1 and No.2 220 kV lines to be vulnerable with a category of probable due to lightning.

Manager NEM Real Time Operations
     
124157RESERVE NOTICE05/02/2025 01:07:47 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1730 hrs 05/02/2025 to 1900 hrs 05/02/2025.
The forecast capacity reserve requirement is 1733 MW.
The minimum capacity reserve available is 1581 MW.

[2.] From 1730 hrs 06/02/2025 to 1900 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1212 MW.


Manager NEM Real Time Operations
     
124152RESERVE NOTICE05/02/2025 11:57:25 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 05/02/2025 to 1900 hrs 05/02/2025.
The forecast capacity reserve requirement is 1754 MW.
The minimum capacity reserve available is 1560 MW.