124240MARKET INTERVENTION06/02/2025 12:48:27 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0730 hrs 07/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
124239SETTLEMENTS RESIDUE06/02/2025 12:35:26 PM

[EventId:202502061235_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 06 February 2025 12:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1235 hrs on 6 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1235 hrs on 6 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124238SETTLEMENTS RESIDUE06/02/2025 12:00:25 PM

[EventId:202502061200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 06 February 2025 12:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1200 hrs on 6 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 February 2025.

Refer to market notice: 124237

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1200 hrs on 6 February 2025.

This is an AEMO autogenerated Market Notice.
     
124237SETTLEMENTS RESIDUE06/02/2025 10:35:29 AM

[EventId:202502061035_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 06 February 2025 10:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1035 hrs on 6 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 6 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1035 hrs on 6 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
124228MARKET INTERVENTION06/02/2025 04:02:44 AM

Cancellation - AEMO Intervention Event - SA region 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 04/02/2025

Refer to Market Notice 124097

The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs on 06/02/2025.


Manager NEM Real Time Operations
     
124227MARKET INTERVENTION06/02/2025 03:56:29 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 124095

Direction is cancelled from: 0400 hrs 06/02/2025

Manager NEM Real Time Operations
     
124218SETTLEMENTS RESIDUE05/02/2025 07:59:38 PM

[EventId:202502051955_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 05 February 2025 19:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1955 hrs on 5 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 February 2025.

Refer to market notice: 124197

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1955 hrs on 5 February 2025.

This is an AEMO autogenerated Market Notice.
     
124204MARKET INTERVENTION05/02/2025 06:16:14 PM

Direction - SA region 05/02/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 05/02/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 05/02/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Market Notice 124182 will now fall under this direction event.

Manager NEM Real Time Operations
     
124203PRICES SUBJECT TO REVIEW05/02/2025 05:56:18 PM

[EventId:202502051800_review] Prices for interval 05-Feb-2025 18:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 5 February 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 05-Feb-2025 18:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm