123767SETTLEMENTS RESIDUE27/01/2025 03:31:46 PM

[EventId:202501271520_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 January 2025 15:20

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1520 hrs on 27 January 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 January 2025.

Refer to market notice: 123759

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1520 hrs on 27 January 2025.

This is an AEMO autogenerated Market Notice.
     
123764INTER-REGIONAL TRANSFER27/01/2025 03:13:20 PM

Inter-regional transfer limit variation - constraint automation to manage Power System Security in VIC region - 27/01/2025

AEMO ELECTRICITY MARKET NOTICE

In order to maintain the power system in a secure operating state in the VIC region, AEMO has invoked automated constraint set CA_BRIS_56A99246_1 from 1450 hrs until further notice.

This constraint set contains equations with the following interconnector on the LHS;

V-S-MNSP1

Manager NEM Real Time Operations
     
123763SETTLEMENTS RESIDUE27/01/2025 03:07:19 PM

[EventId:202501271505_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 27 January 2025 15:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1505 hrs on 27 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 27 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1505 hrs on 27 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123759SETTLEMENTS RESIDUE27/01/2025 01:30:27 PM

[EventId:202501271330_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 27 January 2025 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 27 January 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 January 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1330 hrs on 27 January 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
123758RESERVE NOTICE27/01/2025 01:12:15 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1430 hrs 28/01/2025 to 1630 hrs 28/01/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1064 MW.


Manager NEM Real Time Operations
     
123740RESERVE NOTICE26/01/2025 02:26:06 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1500 hrs 28/01/2025 to 1530 hrs 28/01/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1327 MW.

AEMO Operations
     
123708RESERVE NOTICE25/01/2025 02:29:36 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123675 is cancelled at 1420 hrs 25/01/2025.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
123694RESERVE NOTICE24/01/2025 07:11:31 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 123693 is cancelled at 1910 hrs 24/01/2025.

Manager NEM Real Time Operations
     
123693RESERVE NOTICE24/01/2025 06:16:38 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:


[1.] From 1830 hrs 24/01/2025 to 1900 hrs 24/01/2025.
The forecast capacity reserve requirement is 854 MW.
The minimum capacity reserve available is 816 MW.


Manager NEM Real Time Operations
     