121138GENERAL NOTICE28/11/2024 09:37:07 AM

Planned outage of the Red Cliffs - Wemen - Kerang 220kV line in the VIC region on 30/11/2024.

AEMO ELECTRICITY MARKET NOTICE

The Red Cliffs - Wemen - Kerang 220kV line in the Victorian (VIC) region is planned to be out of service from 0400 hrs to 1430 hrs on 30/11/2024.

A credible contingency event during this planned outage may require:
- Load shedding in the Victorian outer grid; and/ or
- Market intervention, such as the issuing of directions.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
     
120919INTER-REGIONAL TRANSFER25/11/2024 02:03:31 PM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of Murraylink.

The following constraint set was invoked at 1405 hrs 25/11/2024

I-ML_ZERO

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
120836INTER-REGIONAL TRANSFER22/11/2024 07:32:00 PM

Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024

At 1911 hrs 22/11/2024 there was an unplanned outage of the No.2 leg of Directlink.

The following constraint set(s) invoked at 1920 hrs 22/11/2024
N-X_MBTE_2

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
120831INTER-REGIONAL TRANSFER22/11/2024 05:29:01 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 2 Leg of Directlink .

The following constraint set was invoked at 1720 hrs 22/11/2024

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
120800PRICE ADJUSTMENT22/11/2024 11:27:26 AM

[EventId:202411221115_confirmed] Prices for interval 22-Nov-2024 11:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1126 hrs on 22 November 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:15.

In accordance with Market Notice 120795 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs applied. Prices have been carried forward from the previous dispatch interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 $64.00 $25.81
QLD1 $62.79 $26.90
SA1 $8.61 $11.91
VIC1 $8.95 $12.00
LOWER1SEC
NSW1 $0.94 $0.10
QLD1 $0.94 $0.10
SA1 $0.94 $0.10
VIC1 $0.94 $0.10
LOWER60SEC
NSW1 $4.64 $1.82
QLD1 $4.64 $1.82
SA1 $4.64 $1.82
VIC1 $4.64 $1.82
LOWER6SEC
NSW1 $9.69 $4.89
QLD1 $9.69 $4.89
SA1 $9.69 $4.89
VIC1 $9.69 $4.89
LOWERREG
NSW1 $9.99 $19.85
QLD1 $9.99 $19.85
SA1 $9.99 $19.85
VIC1 $9.99 $19.85
RAISE1SEC
NSW1 $0.84 $0.05
QLD1 $0.84 $0.05
SA1 $0.84 $0.05
TAS1 $0.84 $0.05
VIC1 $0.84 $0.05
RAISE5MIN
NSW1 $0.05 $0.10
QLD1 $0.05 $0.10
SA1 $0.05 $0.10
VIC1 $0.05 $0.10
RAISE60SEC
NSW1 $0.00 $0.01
QLD1 $0.00 $0.01
SA1 $0.00 $0.01
VIC1 $0.00 $0.01
RAISE6SEC
NSW1 $0.01 $0.00
QLD1 $0.01 $0.00
SA1 $0.01 $0.00
VIC1 $0.01 $0.00
RAISEREG
NSW1 $7.99 $1.00
QLD1 $7.99 $1.00
SA1 $7.99 $1.00
VIC1 $7.99 $1.00


This is an AEMO autogenerated Market Notice.
     
120797PRICE ADJUSTMENT22/11/2024 11:17:32 AM

[EventId:202411221110_confirmed] Prices for interval 22-Nov-2024 11:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1117 hrs on 22 November 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:10.

In accordance with Market Notice 120794 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs applied. Prices have been carried forward from the previous dispatch interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 $150.01 $25.81
QLD1 $143.43 $26.90
SA1 $53.81 $11.91
VIC1 $55.02 $12.00
LOWER5MIN
NSW1 $1.57 $0.39
QLD1 $1.57 $0.39
SA1 $1.57 $0.39
VIC1 $1.57 $0.39
LOWER60SEC
NSW1 $4.64 $1.82
QLD1 $4.64 $1.82
SA1 $4.64 $1.82
VIC1 $4.64 $1.82
LOWER6SEC
NSW1 $9.69 $4.89
QLD1 $9.69 $4.89
SA1 $9.69 $4.89
VIC1 $9.69 $4.89
LOWERREG
NSW1 $20.90 $19.85
QLD1 $20.90 $19.85
SA1 $20.90 $19.85
VIC1 $20.90 $19.85
RAISE1SEC
NSW1 $0.10 $0.05
QLD1 $0.10 $0.05
SA1 $0.10 $0.05
TAS1 $0.10 $0.05
VIC1 $0.10 $0.05
RAISE5MIN
NSW1 $0.05 $0.10
QLD1 $0.05 $0.10
SA1 $0.05 $0.10
VIC1 $0.05 $0.10
RAISE60SEC
NSW1 $0.05 $0.01
QLD1 $0.05 $0.01
SA1 $0.05 $0.01
VIC1 $0.05 $0.01
RAISE6SEC
NSW1 $0.10 $0.00
QLD1 $0.10 $0.00
SA1 $0.10 $0.00
VIC1 $0.10 $0.00
RAISEREG
NSW1 $5.00 $1.00
QLD1 $5.00 $1.00
SA1 $5.00 $1.00
VIC1 $5.00 $1.00


This is an AEMO autogenerated Market Notice.
     
120724GENERAL NOTICE21/11/2024 12:37:48 PM

Network Augmentation Commissioned - QLD Region - 21/11/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 21/11/2024

Commissioned:

Belmont No.2 275 kV 150 MVar reactor

Manager NEM Real Time Operations
     
120706GENERAL NOTICE20/11/2024 11:00:44 AM

Project Energy Connect (PEC-1) testing 21st November 2024 0600-0900 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 120307

There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 50 MW on 21st November from 06:00hrs to 09:00hrs

This test includes includes a fast runback of Murraylink.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Ben Blake
AEMO Operations
     
120682INTER-REGIONAL TRANSFER19/11/2024 04:44:40 PM

Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Moorabool - Sydenham No. 2 500 kV Line - VIC region - 19/11/2024

A planned outage of Moorabool - Sydenham No. 2 500 kV Line in the VIC region was scheduled from 1130 hrs 13/11/2024 to 1900 hrs 20/11/2024.

The outage has been completed and Moorabool - Sydenham No. 2 500 kV Line returned to service at 1640 hrs 19/11/2024

Constraint set(s) revoked: V-MLSY_NOEMTT_R

Manager NEM Real Time Operations
     