125945INTER-REGIONAL TRANSFER25/03/2025 03:53:45 PM

Inter-regional transfer limit variation - Lower Tumut - Canberra 07 330kV Line - NSW region - 25/03/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lower Tumut - Canberra 07 330kV Line - NSW region - 25/03/2025

A planned outage of Lower Tumut - Canberra 07 330kV Line in the NSW region was scheduled from 1746 hrs 21/03/2025 to 1800 hrs 26/03/2025.

The outage has been completed and Lower Tumut - Canberra 07 330kV Line returned to service at 1555 hrs 25/03/2025

Constraint set(s) revoked: N-CNLT_07

Manager NEM Real Time Operations
     
125943MARKET INTERVENTION25/03/2025 04:01:38 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 125898


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 25/03/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 26/03/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 27/03/2025.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
125942MARKET INTERVENTION25/03/2025 04:01:17 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 125908

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 27/03/2025.

The direction update is issued at 1600 hrs 25/03/2025.

Manager NEM Real Time Operations
     
125940MARKET INTERVENTION25/03/2025 03:58:28 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 125900

Direction is cancelled from: 0400 hrs 25/03/2025

Manager NEM Real Time Operations
     
125908MARKET INTERVENTION24/03/2025 04:01:15 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 125898


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 24/03/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0900 hrs 25/03/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 26/03/2025.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
125906MARKET INTERVENTION24/03/2025 04:01:05 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 125899

The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 26/03/2025.

The direction update is issued at 1600 hrs 24/03/2025.

Manager NEM Real Time Operations
     
125902MARKET INTERVENTION24/03/2025 04:00:50 AM

Cancellation - AEMO Intervention Event - SA region 22/03/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 22/03/2025

Refer to Market Notice 125868

The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs on 24/03/2025.


Manager NEM Real Time Operations
     
125901MARKET INTERVENTION24/03/2025 04:00:40 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 125870

Direction is cancelled from: 0400 hrs 24/03/2025

Manager NEM Real Time Operations
     
125900MARKET INTERVENTION23/03/2025 04:04:08 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 125898


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 23/03/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0900 hrs 24/03/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 25/03/2025.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     