Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Duration: 05/02/2025 12:28 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 05/02/2025 to 1900 hrs 05/02/2025.
The forecast capacity reserve requirement is 1754 MW.
The minimum capacity reserve available is 1560 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124143 has been updated at 1000 hrs 05/02/2025 to the following:
From 1630 hrs to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1161 MW.
The minimum capacity reserve available is 883 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/02/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 124147 is cancelled at 1000 hrs 05/02/2025.
No LOR2 condition is currently forecast in the SA region in the STPASA period.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124146 is cancelled at 1014 hrs 05/02/2025.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/02/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 1800 hrs to 2030 hrs 11/02/2025.
The forecast capacity reserve requirement is 222 MW.
The minimum capacity reserve available is 180 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1500 hrs 05/02/2025 to 1530 hrs 05/02/2025.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 1292 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 124144 is cancelled at 0814 hrs 05/02/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1500 hrs 05/02/2025 to 1530 hrs 05/02/2025.
The forecast capacity reserve requirement is 1360 MW.
The minimum capacity reserve available is 1353 MW.
Manager NEM Real Time Operations