PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123206 is cancelled at 0450 hrs 15/01/2025.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 15 January 2025
NON-CONFORMANCE QLD1 Region Wednesday, 15 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 15/01/2025 01:45 to 15/01/2025 02:05
Amount: 32 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 15 January 2025
NON-CONFORMANCE QLD1 Region Tuesday, 14 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 14/01/2025 23:05 to 15/01/2025 00:05
Amount: 17 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 14 January 2025
NON-CONFORMANCE NSW1 Region Tuesday, 14 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP6
Duration: 14/01/2025 18:00 to 14/01/2025 18:05
Amount: -108 MW
Constraint: NC-N_VP6
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1800 hrs 14/01/2025 to 1900 hrs 14/01/2025.
The forecast capacity reserve requirement is 1580 MW.
The minimum capacity reserve available is 1423 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1630 hrs 15/01/2025 to 1830 hrs 15/01/2025.
The forecast capacity reserve requirement is 1720 MW.
The minimum capacity reserve available is 1570 MW.
Manager NEM Real Time Operations
NEM Local Temperature Alerts for QLD, SA, VIC from 14 Jan 2025 to 18 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Rockhampton Ap (39+ Deg C): 16th Jan
SA
Port Augusta Ap (39+ Deg C): 14th Jan
VIC
Mildura Ap (39+ Deg C): 14th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
NON-CONFORMANCE Region NSW1 Tuesday, 14 January 2025
NON-CONFORMANCE NSW1 Region Tuesday, 14 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 14/01/2025 05:55 to 14/01/2025 06:00
Amount: -19 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 13 January 2025
NON-CONFORMANCE NSW1 Region Monday, 13 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 13/01/2025 19:10 to 13/01/2025 19:20
Amount: -8 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations