125635PRICES SUBJECT TO REVIEW14/03/2025 04:00:14 PM

[EventId:202503141605_review] Prices for interval 14-Mar-2025 16:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 14 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Mar-2025 16:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125634PRICES SUBJECT TO REVIEW14/03/2025 03:55:22 PM

[EventId:202503141600_review] Prices for interval 14-Mar-2025 16:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1555 hrs on 14 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Mar-2025 16:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125633PRICES SUBJECT TO REVIEW14/03/2025 03:50:21 PM

[EventId:202503141555_review] Prices for interval 14-Mar-2025 15:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1550 hrs on 14 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Mar-2025 15:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125632PRICES SUBJECT TO REVIEW14/03/2025 03:45:20 PM

[EventId:202503141550_review] Prices for interval 14-Mar-2025 15:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1545 hrs on 14 March 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 14-Mar-2025 15:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
125625RESERVE NOTICE14/03/2025 01:02:25 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125624 is cancelled at 1200 hrs 14/03/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
125624RESERVE NOTICE14/03/2025 11:08:46 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125622 has been updated at 1000 hrs 14/03/2025 to the following:

From 1730 hrs to 1830 hrs 16/03/2025.
The forecast capacity reserve requirement is 1019 MW.
The minimum capacity reserve available is 845 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
125622RESERVE NOTICE14/03/2025 06:42:24 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 16/03/2025 to 1830 hrs 16/03/2025.
The forecast capacity reserve requirement is 1112 MW.
The minimum capacity reserve available is 1064 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
125619RESERVE NOTICE14/03/2025 04:54:36 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 125607 is cancelled at 0450 hrs 14/03/2025.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
     
125607RESERVE NOTICE13/03/2025 06:27:48 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/03/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1700 hrs 16/03/2025 to 1830 hrs 16/03/2025.
The forecast capacity reserve requirement is 1154 MW.
The minimum capacity reserve available is 948 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm