Filter by category
Filter by Date
NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/12/2024 17:55 to 10/12/2024 18:25
Amount: -18 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412101730_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 December 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 10 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 December 2024.
Refer to market notice: 121699
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1730 hrs on 10 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412101635_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 December 2024 16:35
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 10 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1635 hrs on 10 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
CHG0100201 | Production | Planned maintenance affecting the AEMO Market Network
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network.
Change Start Date & Time: 16/12/2024 08:00:00 AEST
Change End Date & Time: 17/12/2024 17:00:00 AEST
Outage Start Date & Time: 16/12/2024 15:12:00 AEST
Outage End Date & Time: 16/12/2024 15:13:00 AEST
Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 16th of December 2024, between 07:30AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.
During there change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.
Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0100257 | Production | MarketNet Services via Brisbane service disruption for 1-3 seconds as traffic is failed between highly available load balancing services
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: MarketNet Services via Brisbane service disruption for 1-3 seconds as traffic is failed between highly available load balancing services.
Change Start Date & Time: 12/12/2024 14:00:00 AEST
Change End Date & Time: 12/12/2024 16:00:00 AEST
Outage Start Date & Time: 12/12/2024 15:00:00 AEST
Outage End Date & Time: 12/12/2024 15:01:00 AEST
Environment: Production
Participant Impact and Requirements: During there change, there will be a 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Norwest will not be affected during this time.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 10/12/2024 00:55 to 10/12/2024 01:00
Amount: -13 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412091530_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 09 December 2024 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 9 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 9 December 2024.
Refer to market notice: 121655
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1530 hrs on 9 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412091435_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 09 December 2024 14:35
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 9 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 9 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1435 hrs on 9 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Monday, 9 December 2024
NON-CONFORMANCE QLD1 Region Monday, 9 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MIDDLSF1
Duration: 09/12/2024 10:25 to 09/12/2024 11:15
Amount: 22 MW
Constraint: NC-Q_MIDDLSF1
Auto-generated on behalf of Manager NEM Real Time Operations