122435NON-CONFORMANCE23/12/2024 09:40:24 AM

NON-CONFORMANCE Region QLD1 Monday, 23 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 23 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 23/12/2024 09:25 to 23/12/2024 09:40
Amount: 36 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
122318INTER-REGIONAL TRANSFER20/12/2024 03:28:59 PM

Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024

At 1445 hrs 20/12/2024 there was an unplanned outage of South East No.61 Capacitor 275kV.

The following constraint set(s) invoked at 1445 hrs 20/12/2024
S-SE_1CP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
122317INTER-REGIONAL TRANSFER20/12/2024 03:16:23 PM

Update Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024

At 1300 hrs 20/12/2024 there was a short notice outage of Lismore SVC 132kV.

The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
122310INTER-REGIONAL TRANSFER20/12/2024 01:01:43 PM

Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024

At 1300 hrs 20/12/2024 there was a short notice outage of [outage element].

The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
122290NON-CONFORMANCE20/12/2024 03:00:17 AM

NON-CONFORMANCE Region NSW1 Friday, 20 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 20 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 20/12/2024 02:35 to 20/12/2024 03:00
Amount: -27 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
     
122117RESERVE NOTICE17/12/2024 05:44:06 PM

Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) condition in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122113 is cancelled at 1745 hrs 17/12/2024.

Manager NEM Real Time Operations
     
122113RESERVE NOTICE17/12/2024 03:44:28 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 17/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1082 MW

Manager NEM Real Time Operations
     
122049RESERVE NOTICE16/12/2024 06:40:21 PM

Cancellation of Actual (LOR1) condition in the NSW region - 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 16/12/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.122029 is cancelled at 1835 hrs 16/12/2024.

Manager NEM Real Time Operations
     
122029RESERVE NOTICE16/12/2024 05:21:43 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1297 MW