Inter-regional transfer limit variation - Red Cliffs - Wemen 220 kV line - VIC region - 30/11/2024
Inter-regional transfer limit variation - Red Cliffs - Wemen 220 kV line - VIC region - 30/11/2024
A planned outage of Red Cliffs - Wemen 220 kV line in the VIC region was scheduled from 0400 hrs 30/11/2024 to 1430 hrs 30/11/2024.
The outage has been completed and Red Cliffs - Wemen 220 kV line returned to service at 1120 hrs 30/11/2024
Constraint set(s) revoked: V-KG_WE_RC
Manager NEM Real Time Operations
Cancellation - Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024
Refer AEMO Electricity Market Notice 121142
Constraint set I-QN_1000 was invoked from 0955 hrs until 1230 hrs 28/11/2024.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - to manage Power System Security in NSW region - 28/11/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked the following constraint set I-QN_1000 from 0955 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
NSW1-QLD1
Manager NEM Real Time Operations
Planned outage of the Red Cliffs - Wemen - Kerang 220kV line in the VIC region on 30/11/2024.
The Red Cliffs - Wemen - Kerang 220kV line in the Victorian (VIC) region is planned to be out of service from 0400 hrs to 1430 hrs on 30/11/2024.
A credible contingency event during this planned outage may require:
- Load shedding in the Victorian outer grid; and/ or
- Market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121040 is cancelled at 1130 hrs 27/11/2024
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121021 has been updated at 1000 hrs to the following:
[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 1530 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1330 hrs.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 27/11/2024
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1530 hrs 27/11/2024 to 1700 hrs 27/11/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 84 MW at approximately 1530 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 26/11/2024
Non-credible contingency event - NSW region - 26/11/2024
At 1637 hrs Uranquinty Unit 12 tripped and at 1639 hrs Uranquinty Units 11 and 13 tripped.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 28/11/2024
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 120965 is cancelled at 1200 hrs on 26/11/2024.
No LOR3 condition is currently forecast in the STPASA period.
AEMO Operations