Inter-regional transfer limit variation - Armidale - Tamworth No. 86 330 kV Line - NSW region - 01/02/2025
Inter-regional transfer limit variation - Armidale - Tamworth No. 86 330 kV Line - NSW region - 01/02/2025
A planned outage of Armidale - Tamworth No. 86 330 kV Line in the NSW region was scheduled to be completed at 1030 hrs 01/02/2025
The outage has been completed by 0835 hrs 01/02/2025
Constraint set(s) invoked:
N-ARTW_86
N-DM_SVC
N-TW_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0030 hrs 02/02/2025.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 123925
Direction is cancelled from: 0400 hrs 01/02/2025
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123924
PPCCGT PELICAN POINT at 0100 hrs 27/01/2025 to Remain synchronised and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 1600 hrs 01/02/2025.
The direction update is issued at 1600 hrs 31/01/2025.
Manager NEM Real Time Operations
Project Energy Connect (PEC-1) testing 31th January 2025 1100-1500 for flows from South Australia to Victoria direction up to 150 MW
Refer to market notice 123676
There is an opportunity for testing Project Energy Connect (PEC-1) for flows from South Australia to Victoria direction up to 150 MW on 31th January from 11:00hrs to 15:00hrs
This test includes switching of transmission lines and reactive plant in South Australia and in New South Wales.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
AEMO Operations
NEM Local Temperature Alerts for SA, TAS, VIC from 31 Jan 2025 to 04 Feb 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 3rd Feb
Clare High School (39+ Deg C): 2nd Feb, 3rd Feb, 4th Feb
Mt Gambier Ap (39+ Deg C): 2nd Feb, 3rd Feb
Port Augusta Ap (39+ Deg C): 1st Feb, 2nd Feb, 3rd Feb, 4th Feb
TAS
Launceston Ti Tree Bend (33+ Deg C): 2nd Feb, 3rd Feb, 4th Feb
VIC
Latrobe Valley Ap (39+ Deg C): 2nd Feb
Mildura Ap (39+ Deg C): 1st Feb, 2nd Feb, 3rd Feb, 4th Feb
Mortlake (39+ Deg C): 3rd Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 2 Leg of Directlink .
The following constraint set was invoked at 1525 hrs 30/01/2025
N-X_MBTE_2
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 123884
TORRB2 TORRENS ISLAN at 0030 hrs 27/01/2025 to Remain synchronized and follow dispatch targets.
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 01/02/2025.
The direction update is issued at 1600 hrs 30/01/2025.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123885
PPCCGT PELICAN POINT at 0100 hrs 27/01/2025 to Remain synchronized and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 01/02/2025.
The direction update is issued at 1600 hrs 30/01/2025.
Manager NEM Real Time Operations