124131RESERVE NOTICE04/02/2025 05:46:30 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1161 MW

Manager NEM Real Time Operations
     
124117NON-CONFORMANCE04/02/2025 04:05:34 PM

NON-CONFORMANCE Region QLD1 Tuesday, 4 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 4 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 04/02/2025 15:50 to 04/02/2025 16:00
Amount: 35 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
     
124065NON-CONFORMANCE04/02/2025 12:15:15 PM

NON-CONFORMANCE Region NSW1 Tuesday, 4 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 4 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 04/02/2025 12:05 to 04/02/2025 12:15
Amount: -57 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124041NON-CONFORMANCE03/02/2025 10:46:30 AM

NON-CONFORMANCE Region NSW1 Monday, 3 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 3 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 03/02/2025 10:35 to 03/02/2025 10:40
Amount: -132 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123957NON-CONFORMANCE31/01/2025 11:31:33 AM

NON-CONFORMANCE Region NSW1 Friday, 31 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 31 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 31/01/2025 11:05 to 31/01/2025 11:30
Amount: -226 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123917NON-CONFORMANCE30/01/2025 06:50:11 AM

NON-CONFORMANCE Region NSW1 Thursday, 30 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 30 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 30/01/2025 06:45 to 30/01/2025 06:50
Amount: -14 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123843NON-CONFORMANCE29/01/2025 08:40:11 AM

NON-CONFORMANCE Region NSW1 Wednesday, 29 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 29 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: CAPBES1
Duration: 29/01/2025 08:35 to 29/01/2025 08:40
Amount: -100 MW
Constraint: NC-N_CAPBES1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123820NON-CONFORMANCE28/01/2025 06:10:14 PM

NON-CONFORMANCE Region QLD1 Tuesday, 28 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 28 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 28/01/2025 17:55 to 28/01/2025 18:10
Amount: -17 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
123768NON-CONFORMANCE27/01/2025 03:45:18 PM

NON-CONFORMANCE Region SA1 Monday, 27 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 27 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: HPR1
Duration: 27/01/2025 15:40 to 27/01/2025 15:45
Amount: 12 MW
Constraint: NC-S_HPR1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm