Market Notices

125294RECLASSIFY CONTINGENCY05/03/2025 07:19:30 PM

Cancellation of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Cancellation time: 05/03/2025 19:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 125276

Auto-generated on behalf of Manager NEM Real Time Operations
     
125292PRICES UNCHANGED05/03/2025 06:25:19 PM

[EventId:202503051805_confirmed] Prices for interval 05-Mar-2025 18:05 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 5 March 2025

PRICES ARE NOW CONFIRMED for trading interval 05-Mar-2025 18:05.

In accordance with Market Notice 125281 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125291PRICES UNCHANGED05/03/2025 06:25:20 PM

[EventId:202503051825_confirmed] Prices for interval 05-Mar-2025 18:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 5 March 2025

PRICES ARE NOW CONFIRMED for trading interval 05-Mar-2025 18:25.

In accordance with Market Notice 125286 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125290PRICES UNCHANGED05/03/2025 06:25:20 PM

[EventId:202503051820_confirmed] Prices for interval 05-Mar-2025 18:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 5 March 2025

PRICES ARE NOW CONFIRMED for trading interval 05-Mar-2025 18:20.

In accordance with Market Notice 125285 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125289PRICES UNCHANGED05/03/2025 06:25:20 PM

[EventId:202503051815_confirmed] Prices for interval 05-Mar-2025 18:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 5 March 2025

PRICES ARE NOW CONFIRMED for trading interval 05-Mar-2025 18:15.

In accordance with Market Notice 125284 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125288PRICES UNCHANGED05/03/2025 06:25:20 PM

[EventId:202503051810_confirmed] Prices for interval 05-Mar-2025 18:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 5 March 2025

PRICES ARE NOW CONFIRMED for trading interval 05-Mar-2025 18:10.

In accordance with Market Notice 125283 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125287PRICES UNCHANGED05/03/2025 06:25:13 PM

[EventId:202503051800_confirmed] Prices for interval 05-Mar-2025 18:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1825 hrs on 5 March 2025

PRICES ARE NOW CONFIRMED for trading interval 05-Mar-2025 18:00.

In accordance with Market Notice 125280 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
125276RECLASSIFY CONTINGENCY05/03/2025 04:14:25 PM

Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Duration: 05/03/2025 16:14 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
125273POWER SYSTEM EVENTS05/03/2025 02:03:49 PM

Update - Non-credible contingency event - NSW region - 05/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - NSW region - 05/03/2025

Refer AEMO Electricity Market Notice 125268

At 1400 hrs the Directlink DC1 was returned to service.

(At 1030 hrs the Ewingsdale-Mullumbimby 9G5 132kV line was returned to service.)

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     