Market Notices

125085MARKET INTERVENTION25/02/2025 02:18:49 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 125084

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 26/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 25/02/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
125084MARKET INTERVENTION25/02/2025 01:01:24 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0800 hrs 26/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
125083NON-CONFORMANCE25/02/2025 11:00:18 AM

NON-CONFORMANCE Region VIC1 Tuesday, 25 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 25 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOKOSF1
Duration: 25/02/2025 09:50 to 25/02/2025 11:00
Amount: 32 MW
Constraint: NC-V_MOKOSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125082NON-CONFORMANCE25/02/2025 10:20:17 AM

NON-CONFORMANCE Region QLD1 Tuesday, 25 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 25 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STAN-4
Duration: 25/02/2025 09:30 to 25/02/2025 10:20
Amount: -18 MW
Constraint: NC-Q_STAN-4

Auto-generated on behalf of Manager NEM Real Time Operations
     
125076SETTLEMENTS RESIDUE24/02/2025 05:30:25 PM

[EventId:202502241730_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 February 2025 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 24 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.

Refer to market notice: 125075

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1730 hrs on 24 February 2025.

This is an AEMO autogenerated Market Notice.
     
125075SETTLEMENTS RESIDUE24/02/2025 03:40:17 PM

[EventId:202502241540_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 24 February 2025 15:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1540 hrs on 24 February 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1540 hrs on 24 February 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
125074SETTLEMENTS RESIDUE24/02/2025 03:30:23 PM

[EventId:202502241530_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 February 2025 15:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 24 February 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 February 2025.

Refer to market notice: 125071

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 1530 hrs on 24 February 2025.

This is an AEMO autogenerated Market Notice.
     
125073MARKET INTERVENTION24/02/2025 03:57:33 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 125053

TORRB2 TORRENS ISLAN at 0030 hrs 23/02/2025 to Remain synchronised and follow dispatch targets.

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 25/02/2025.

The direction update is issued at 1600 hrs 24/02/2025.

Manager NEM Real Time Operations
     
125072MARKET INTERVENTION24/02/2025 03:57:16 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 125060

PPCCGT PELICAN POINT at 0730 hrs 24/02/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 1500 hrs 25/02/2025.

The direction update is issued at 1600 hrs 24/02/2025.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm