STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 16/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121694 has been updated at 1900 hrs 10/12/2024 to the following:
[1.] From 1700 hrs 16/12/2024 to 1900 hrs 16/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 318 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 10 December 2024
NON-CONFORMANCE QLD1 Region Tuesday, 10 December 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/12/2024 17:55 to 10/12/2024 18:25
Amount: -18 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412101730_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 December 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 10 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 December 2024.
Refer to market notice: 121699
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1730 hrs on 10 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412101635_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 December 2024 16:35
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 10 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1635 hrs on 10 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/12/2024
Cancellation - Possible intervention to manage power system security in South Australia (SA) region 11/12/2024
Refer Market Notice 121685
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1615 hrs 10/12/2024.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121687 has been updated at 1400 hrs 10/12/2024 to the following:
1. From 1630 hrs to 1930 hrs 16/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 277 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update and correction of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/12/2024
Correction to Market Notice 121686, the external reference for the forecast LOR2 in the NSW region should read: 16/12/2024.
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121686 has been updated at 1200 hrs 10/12/2024 to the following:
1. From 1730 hrs to 1830 hrs 16/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 592 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 16/10/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 121683 has been updated at 0800hrs 10/12/2024 to the following:
1. From 1700 hrs to 1900 hrs 16/12/2024.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 336 MW.
AEMO is seeking a market response.
AEMO Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 11/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations