121295RESERVE NOTICE30/11/2024 04:40:16 PM

STPASA - Update of the suspect Lack Of Reserve Level 3 (LOR3) condition in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

The suspect LOR3 condition advised in AEMO Electricity Market Notice No. 121292 has been reviewed.

AEMO considers this forecast LOR3 condition invalid. Subsequent STPASA runs are producing valid solutions.


AEMO Operations
     
121292RESERVE NOTICE30/11/2024 02:52:04 PM

STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO considers that there is a suspect Forecast LOR3 condition for the NSW region for the following period:

From 1630 hrs 06/12/2024 to 1700 hrs 06/12/2024.

AEMO is currently investigating this LOR3 forecast condition to confirm whether they are valid.


AEMO Operations
     
121285MARKET INTERVENTION30/11/2024 09:30:31 AM

Cancellation - Foreseeable intervention to manage power system security in SA region 30/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Foreseeable intervention to manage power system security in SA region 30/11/2024

Refer Market Notice 121281

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 0915 hrs 30/11/2024.

Manager NEM Real Time Operations
     
121281MARKET INTERVENTION30/11/2024 08:19:02 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 121280

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1100 hrs 30/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 0900 hrs 30/11/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
121280MARKET INTERVENTION30/11/2024 08:09:12 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1100 hrs 30/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
121169PRICE ADJUSTMENT28/11/2024 02:18:30 PM

[EventId:202411271510_confirmed] Prices for interval 27-Nov-2024 15:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1418 hrs on 28 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 15:10.

In accordance with Market Notice 121092 AEMO has reviewed this trading interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
VIC1 -$30.00 -$29.50
RAISE60SEC
NSW1 $0.10 $0.05
QLD1 $0.10 $0.05
SA1 $0.10 $0.05
VIC1 $0.10 $0.05


This is an AEMO autogenerated Market Notice.
     
121167MARKET INTERVENTION28/11/2024 03:01:25 PM

Cancellation - AEMO Intervention Event - SA region 27/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 27/11/2024

Refer to Market Notice 121094

The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 28/11/2024.


Manager NEM Real Time Operations
     
121166MARKET INTERVENTION28/11/2024 02:59:59 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 121091

Direction is cancelled from: 1500 hrs 28/11/2024

Manager NEM Real Time Operations
     
121165MARKET INTERVENTION28/11/2024 02:29:51 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 121090

Direction is cancelled from: 1430 hrs 28/11/2024

Manager NEM Real Time Operations
     