Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 123925
Direction is cancelled from: 0400 hrs 01/02/2025
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123924
PPCCGT PELICAN POINT at 0100 hrs 27/01/2025 to Remain synchronised and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 1600 hrs 01/02/2025.
The direction update is issued at 1600 hrs 31/01/2025.
Manager NEM Real Time Operations
CHG0101137 | Production | Planned Maintenance to Norwest Marketnet Site to Site VPN Router
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: Planned Maintenance to Norwest Marketnet Site to Site VPN Router
Change Start Date & Time: 04/02/2025 11:00:00 AEST
Change End Date & Time: 04/02/2025 15:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned maintenance:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Nil
B2B VPN - Nil
SSL VPN Participants: Nil
GASHUB: Nil
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 123884
TORRB2 TORRENS ISLAN at 0030 hrs 27/01/2025 to Remain synchronized and follow dispatch targets.
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 01/02/2025.
The direction update is issued at 1600 hrs 30/01/2025.
Manager NEM Real Time Operations
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 123885
PPCCGT PELICAN POINT at 0100 hrs 27/01/2025 to Remain synchronized and follow dispatch targets.
The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 01/02/2025.
The direction update is issued at 1600 hrs 30/01/2025.
Manager NEM Real Time Operations
[EventId:202501301330_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 January 2025 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 30 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 January 2025.
Refer to market notice: 123921
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1330 hrs on 30 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501301210_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 January 2025 12:10
Issued by Australian Energy Market Operator Ltd at 1210 hrs on 30 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1210 hrs on 30 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501301200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 January 2025 12:00
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 30 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 January 2025.
Refer to market notice: 123918
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1200 hrs on 30 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501301100_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 January 2025 11:00
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 30 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1100 hrs on 30 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.