Market Notices

123441MARKET INTERVENTION18/01/2025 12:26:56 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123439


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1230 hrs 18/01/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0000 hrs 19/01/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 19/01/2025.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
123439MARKET INTERVENTION18/01/2025 08:10:48 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 123438

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0000 hrs 19/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1230 hrs 18/01/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
123438MARKET INTERVENTION18/01/2025 07:46:08 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0000 hrs 19/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
123408MARKET INTERVENTION17/01/2025 02:52:11 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123385

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 18/01/2025.

The direction update is issued at 1500 hrs 17/01/2025.

Manager NEM Real Time Operations
     
123407MARKET INTERVENTION17/01/2025 02:50:54 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123384

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1430 hrs 18/01/2025.

The direction update is issued at 1500 hrs 17/01/2025.

Manager NEM Real Time Operations
     
123385MARKET INTERVENTION16/01/2025 04:57:24 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123293

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 18/01/2025.

The direction update is issued at 1700 hrs 16/01/2025.

Manager NEM Real Time Operations
     
123384MARKET INTERVENTION16/01/2025 04:56:07 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 123292

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 18/01/2025.

The direction update is issued at 1700 hrs 16/01/2025.

Manager NEM Real Time Operations
     
123326PRICES SUBJECT TO REVIEW15/01/2025 04:55:28 PM

[EventId:202501151700_review] Prices for interval 15-Jan-2025 17:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1655 hrs on 15 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 17:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123324PRICES SUBJECT TO REVIEW15/01/2025 04:50:21 PM

[EventId:202501151655_review] Prices for interval 15-Jan-2025 16:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1650 hrs on 15 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     