123613POWER SYSTEM EVENTS23/01/2025 03:02:44 AM

Non-credible contingency event - NSW region - 23/01/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - NSW region - 23/01/2025

At 0240 hrs the Kempsey - Macksville 9W5 and the Kempsey - Raleigh 9W2 132kV Lines tripped and auto reclosed.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
123602RESERVE NOTICE22/01/2025 08:14:17 PM

Cancellation of Actual (LOR1) condition in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 22/01/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.123589 is cancelled at 2015 hrs 22/01/2025.

Manager NEM Real Time Operations
     
123598RESERVE NOTICE22/01/2025 07:44:15 PM

Cancellation of Actual (LOR2) condition in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the QLD region - 22/01/2025

The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No.123594 is cancelled at 1945 hrs 22/01/2025.

Manager NEM Real Time Operations
     
123594RESERVE NOTICE22/01/2025 06:43:09 PM

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 22/01/2025

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1830 hrs.

The Actual LOR2 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 515 MW.
The minimum capacity reserve available is 395 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement an AEMO intervention event.

Manager NEM Real Time Operations
     
123589RESERVE NOTICE22/01/2025 05:47:39 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 854 MW
The minimum capacity reserve available is 543 MW

Manager NEM Real Time Operations
     
123550NON-CONFORMANCE22/01/2025 09:00:31 AM

NON-CONFORMANCE Region NSW1 Wednesday, 22 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 22 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 22/01/2025 08:50 to 22/01/2025 09:00
Amount: 18 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
123547NON-CONFORMANCE22/01/2025 06:45:21 AM

NON-CONFORMANCE Region QLD1 Wednesday, 22 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 22 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 22/01/2025 06:40 to 22/01/2025 06:45
Amount: 16 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123535NON-CONFORMANCE21/01/2025 06:40:24 PM

NON-CONFORMANCE Region NSW1 Tuesday, 21 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 21 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TALWA1
Duration: 21/01/2025 18:35 to 21/01/2025 18:40
Amount: 44 MW
Constraint: NC-N_TALWA1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123521NON-CONFORMANCE21/01/2025 01:55:12 PM

NON-CONFORMANCE Region QLD1 Tuesday, 21 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 21 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 21/01/2025 09:45 to 21/01/2025 13:55
Amount: 36 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm