Filter by category
Filter by Date
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 24/01/2025
The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 123637 is cancelled at 0445 hrs 24/01/2025
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 24/01/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1900 hrs 24/01/2025 to 1930 hrs 24/01/2025.
The forecast capacity reserve requirement is 854 MW.
The minimum capacity reserve available is 830 MW.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 28/01/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123523 is cancelled at 1400 hrs 23/01/2025.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
NEM Local Temperature Alerts for QLD, SA, VIC from 23 Jan 2025 to 27 Jan 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
QLD
Dalby Ap (37+ Deg C): 23rd Jan, 24th Jan
Rockhampton Ap (39+ Deg C): 23rd Jan, 24th Jan
SA
Port Augusta Ap (39+ Deg C): 26th Jan, 27th Jan
VIC
Latrobe Valley Ap (39+ Deg C): 27th Jan
Mildura Ap (39+ Deg C): 27th Jan
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Cancellation of Actual (LOR1) condition in the QLD region - 22/01/2025
Cancellation of Actual (LOR1) condition in the QLD region - 22/01/2025
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.123589 is cancelled at 2015 hrs 22/01/2025.
Manager NEM Real Time Operations
Cancellation of Actual (LOR2) condition in the QLD region - 22/01/2025
Cancellation of Actual (LOR2) condition in the QLD region - 22/01/2025
The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No.123594 is cancelled at 1945 hrs 22/01/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 22/01/2025
Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 22/01/2025
An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1830 hrs.
The Actual LOR2 condition is forecast to exist until 1900 hrs.
The forecast capacity reserve requirement is 515 MW.
The minimum capacity reserve available is 395 MW.
AEMO is seeking an immediate market response.
An insufficient market response may require AEMO to implement an AEMO intervention event.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 854 MW
The minimum capacity reserve available is 543 MW
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 22/01/2025
The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 123581 has been updated at 1650 hrs to the following:
From 1800 hrs 22/01/2025 to 1930 hrs 22/01/2025.
The forecast capacity reserve requirement is 856 MW.
The minimum capacity reserve available is 709 MW.
Manager NEM Real Time Operations