122326MARKET SYSTEMS20/12/2024 04:16:29 PM

INC0139532 | Impact to Prudentials

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - ALERT

The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
     
122281MARKET SYSTEMS19/12/2024 04:40:39 PM

INC0139532 - ALERT - Impact to Prudentials

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - ALERT

AEMO is experiencing a service interruption relating to: Prudentials & Settlements.

AEMO is working on the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600

Email: supporthub@aemo.com.au

AEMO IT Duty Manager
     
122047MARKET SYSTEMS16/12/2024 06:07:34 PM

CHG0100502 | Production | Planned maintenance affecting the AEMO Market Network.

Change Number: CHG0100502
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network ***Outage Updated***
Change Start Date & Time: 19/12/2024 07:00:00 AEST
Change End Date & Time: 20/12/2024 17:00:00 AEST
Outage 1 Start Date & Time: 19/12/2024 09:12:00 AEST
Outage 1 End Date & Time: 19/12/2024 09:13:00 AEST
Outage 2 Start Date & Time: 19/12/2024 15:12:00 AEST
Outage 2 End Date & Time: 19/12/2024 15:13:00 AEST

Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 19th of December 2024, between 07:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.

During there change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.

Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .

     
121833RESERVE NOTICE13/12/2024 01:08:53 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121818 is cancelled at 1200 hrs on 13/12/2024.

No LOR3 condition is currently forecast in the STPASA period.

AEMO Operations
     
121831RESERVE NOTICE13/12/2024 01:06:24 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121817 is cancelled at 1200 hrs on 13/12/2024.

No LOR3 condition is currently forecast in the STPASA period.

AEMO Operations
     
121827RESERVE NOTICE13/12/2024 09:16:31 AM

STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 121817 has been updated at 0800 hrs 13/12/2024 to the following:

From 1630 hrs to 1900 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 321 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
121818RESERVE NOTICE13/12/2024 04:57:28 AM

STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1500 hrs 17/12/2024 to 1900 hrs 17/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 376 MW at 1630 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121817RESERVE NOTICE13/12/2024 05:02:20 AM

STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1600 hrs 16/12/2024 to 1900 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 573 MW at 1730 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
121806POWER SYSTEM EVENTS12/12/2024 08:52:19 PM

Non-credible contingency event - QLD region - 12/12/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 12/12/2024

At 2026 hrs the Kamerunga to Barron George 132 kV Line 7184 and the Kamerunga to Barron George 132 kV Line 7141 tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     