123672MARKET INTERVENTION24/01/2025 03:58:18 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123624

TORRB3 TORRENS ISLAN at 0400 hrs 25/01/2025 to Remain synchronised and follow dispatch targets.

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 26/01/2025.

The direction update is issued at 1600 hrs 24/01/2025.

Manager NEM Real Time Operations
     
123669MARKET SYSTEMS24/01/2025 01:50:35 PM

CHG0100610 | Production | Planned Maintenance to Brisbane Internet Router

Change Number: CHG0100610
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: Planned Maintenance to Brisbane Internet Router
Change Start Date & Time: 01/02/2025 11:00:57 AEST
Change End Date & Time: 01/02/2025 13:00:57 AEST
Outage Start Date & Time: 01/02/2025 11:00:31 AEST
Outage End Date & Time: 01/02/2025 13:00:31 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - Nil

Lan-2-Lan VPN Participants (IPSEC) - Up to 1 Hour outage for participants who have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10 for Policy Based VPN and 202.44.76.12 for Route Based VPN) only - All L2L connections should be established to both QLD / NSW.

B2B VPN - Up to 1 hour outage to TNSPs with B2B VPN to AEMO QLD Datacentre if VPN connection is only terminating in QLD only.

SSL VPN Participants: None expected as DNS entry will be updated to remove QLD IP.

GASHUB: Nil

Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point 202.44.78.10 for Policy Based VPN and 202.44.78.12 for Route Based VPN) prior to this scheduled outage.

*** Failure to do so will impact connectivity to Marketnet Services. ***

Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .

     
123668MARKET SYSTEMS24/01/2025 01:45:37 PM

CHG0100719 | Production | Participant FTP File Server Maintenance

Change Number: CHG0100719
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: Participant FTP File Server Maintenance
Change Start Date & Time: 29/01/2025 10:00:00 AEST
Change End Date & Time: 29/01/2025 11:00:00 AEST
Outage Start Date & Time: 29/01/2025 10:15:00 AEST
Outage End Date & Time: 29/01/2025 10:15:30 AEST
Environment: Production
Participant Impact and Requirements: All external participants will be briefly disconnected (up to 30 seconds) and then automatically reconnected.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .

     
123646MARKET SYSTEMS24/01/2025 07:21:37 AM

CHG0100766 | Completed | Production | Planned Maintenance to Brisbane ISE Server

Change Number: CHG0100766
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Planned Maintenance to Brisbane ISE Server
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
123639NON-CONFORMANCE23/01/2025 07:10:20 PM

NON-CONFORMANCE Region NSW1 Thursday, 23 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 23 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 23/01/2025 19:05 to 23/01/2025 19:10
Amount: -25 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
123638NON-CONFORMANCE23/01/2025 05:30:16 PM

NON-CONFORMANCE Region NSW1 Thursday, 23 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 23 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 23/01/2025 17:25 to 23/01/2025 17:30
Amount: 15 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
123624MARKET INTERVENTION23/01/2025 02:57:06 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 123579

TORRB3 TORRENS ISLAN at 0400 hrs 24/01/2025 to Remain synchronised and follow dispatch targets.

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 25/01/2025.

The direction update is issued at 1500 hrs 23/01/2025.

Manager NEM Real Time Operations
     
123623MARKET INTERVENTION23/01/2025 02:55:48 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123618

PPCCGT PELICAN POINT at 1800 hrs 23/01/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 1730 hrs 24/01/2025.

The direction update is issued at 1500 hrs 23/01/2025.

Manager NEM Real Time Operations
     
123621NON-CONFORMANCE23/01/2025 10:25:24 AM

NON-CONFORMANCE Region QLD1 Thursday, 23 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 23 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 23/01/2025 08:40 to 23/01/2025 10:25
Amount: -35 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     