Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1214 MW
Manager NEM Real Time Operations
[EventId:202502051735_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 05 February 2025 17:35
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 5 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1735 hrs on 5 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
CHG0100111 | Pre-Production | Pre-Prod eMDM February Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM February Maintenance Release
Change Start Date & Time: 11/02/2025 13:00:00 AEST
Change End Date & Time: 11/02/2025 17:00:00 AEST
Outage Start Date & Time: 11/02/2025 13:00:00 AEST
Outage End Date & Time: 11/02/2025 15:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
[EventId:202502051545_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 05 February 2025 15:45
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 5 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 February 2025.
Refer to market notice: 124174
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1545 hrs on 5 February 2025.
This is an AEMO autogenerated Market Notice.
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 07/02/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 124154 has been updated at 1500 hrs 05/02/2025 to the following:
From 1630 hrs to 1900 hrs 07/02/2025.
The forecast capacity reserve requirement is 1162 MW.
The minimum capacity reserve available is 842 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025
Cancellation of Actual (LOR1) condition in the NSW region - 05/02/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124176 is cancelled at 1444 hrs 05/02/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/02/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1330 hrs.
The Actual LOR1 condition is forecast to exist until 1430 hrs
The capacity reserve requirement is 1320 MW
The minimum capacity reserve available is 1254 MW
Manager NEM Real Time Operations
[EventId:202502051330_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 05 February 2025 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 5 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1330 hrs on 5 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502051300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 05 February 2025 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 5 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 5 February 2025.
Refer to market notice: 124151
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 5 February 2025.
This is an AEMO autogenerated Market Notice.