Filter by category
Filter by Date
Inter-regional transfer limit variation - Directlink- NSW region - 13/02/2025
Inter-regional transfer limit variation - No.2 Leg of Directlink - NSW region - 13/02/2025
A planned outage of the No.2 Leg of Directlink in the NSW region was scheduled from 1517 hrs 30/01/2025 to 1700 hrs 20/02/2025.
The outage has been completed and the No.2 Leg of Directlink returned to service at 1312 hrs 13/02/2025
Constraint set(s) revoked: N-X_MBTE_2
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Armidale No 1 SVC- NSW region - 11/02/2025
Inter-regional transfer limit variation - Armidale No 1 SVC - NSW region - 11/02/2025
At 2315 hrs 11/02/2025 there was an unplanned outage of Armidale No 1 SVC.
The following constraint set(s) invoked at 2325 hrs 11/02/2025
N-AR_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Yass Overload Control Scheme - NSW region - 11/02/2025
Inter-regional transfer limit variation - Yass Overload Control Scheme - NSW region - 11/02/2025
At 1750 hrs 11/02/2025 there was a short notice outage of Yass Overload Control Scheme.
The following constraint set(s) invoked at 1750 hrs: N-YSWG_SCHEME
This constraint set(s) contains equations with the following interconnectors on the LHS,
V-S-MNSP1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025
Inter-regional transfer limit variation - MLTS-SMTS No1 500 kV line CB at SYTS - VIC region - 11/02/2025
At 1538 hrs 11/02/2025 there was an unplanned outage of MLTS-SMTS No1 500 kV line CB at SYTS .
The following constraint set(s) invoked at 1600 hrs 11/02/2025
V-SY_CB
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation - Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025
Referring to Market Notice 124466.
The power system security condition in the SA region, requiring AEMO to invoke the automated constraint set CA_SYDS_56BD5936 has ended at 1520 hrs.
Constraint set revoked: CA_SYDS_56BD5936
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 11/02/2025
In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked automated constraint set CA_SYDS_56BD5936 from 1410 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
V-SA
Manager NEM Real Time Operations
CHG0100111 | Completed | Pre-Production | Pre-Prod eMDM February Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM February Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NON-CONFORMANCE Region NSW1 Tuesday, 11 February 2025
NON-CONFORMANCE NSW1 Region Tuesday, 11 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 11/02/2025 13:55 to 11/02/2025 14:00
Amount: -11 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502101600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 February 2025 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 10 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Refer to market notice: 124442
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 10 February 2025.
This is an AEMO autogenerated Market Notice.