Market Notices

126309SETTLEMENTS RESIDUE04/04/2025 06:30:30 PM

[EventId:202504041830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 04 April 2025 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 4 April 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.

Refer to market notice: 126297

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 4 April 2025.

This is an AEMO autogenerated Market Notice.
     
126297SETTLEMENTS RESIDUE04/04/2025 05:05:15 PM

[EventId:202504041705_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 04 April 2025 17:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1705 hrs on 4 April 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 4 April 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1705 hrs on 4 April 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
126291MARKET SYSTEMS04/04/2025 03:33:34 PM

Inital - CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0101896


Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:

3/04/2025
7/04/2025
8/04/2025


During the window,FPP calculations may be delayed at various points.


Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
126275MARKET SYSTEMS04/04/2025 09:23:36 AM

Inital - CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0101896


Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00

Environment: Pre-Production

Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:

3/04/2025
7/04/2025
8/04/2025

During the window,FPP calculations may be delayed at various points.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
126244MARKET SYSTEMS03/04/2025 01:15:02 PM

Create Market Notice - Completed - CHG0099569 - Maintenance on Gas B2B Hub databases

Change Number: CHG0099569

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: Maintenance on Gas B2B Hub databases

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
126243MARKET SYSTEMS03/04/2025 01:14:06 PM

Create Market Notice - Inital - CHG0102439 - NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Mondday 7 April until 12pm (EST)

Change Number: CHG0102439

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Supply Hub
Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Mondday 7 April until 12pm (EST)

Change Start Date & Time: 07/04/2025 09:00:00
Change End Date & Time: 07/04/2025 12:00:00
Outage Start Date & Time: 07/04/2025 09:00:00
Outage End Date & Time: 07/04/2025 12:00:00
Environment: Pre-Production
Participant Impact and Requirements: Services may be unavailable while maintenance is in progress

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities
     
126242MARKET SYSTEMS03/04/2025 01:11:40 PM

Create Market Notice - Inital - CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0101896

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:

3/04/2025
7/04/2025
8/04/2025

During the window,FPP calculations may be delayed at various points.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
126240MARKET SYSTEMS03/04/2025 08:23:08 AM

Create Market Notice - Completed - CHG0102343 - Frequency Performance Payments (FPP) Maintenance Release

Change Number: CHG0102343

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Frequency Performance Payments Engine
Change Title: Frequency Performance Payments (FPP) Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
126224MARKET SYSTEMS02/04/2025 03:50:03 PM

Create Market Notice - Inital - CHG0101896 - EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .

Change Number: CHG0101896

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System_PreProd
Change Title: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities .
Change Start Date & Time: 01/04/2025 08:00:00
Change End Date & Time: 11/04/2025 17:00:00
Outage Start Date & Time: 03/04/2025 08:00:00
Outage End Date & Time: 03/04/2025 22:00:00
Environment: Pre-Production
Participant Impact and Requirements: EMMS Pre-Production Systems will be transferred to the alternative datacentre for maintenance activities. Maintenance activities will be conducted on the following dates:

3/04/2025
7/04/2025
8/04/2025

During the window,FPP calculations may be delayed at various points.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm