Filter by category
Filter by Date
Completed - CHG0102537 - NOR Pre-Prod GFRC will have scheduled maintenance works outage from 9.00am Wednesday 9 April until 12pm (EST)
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Windows Server
Change Title: NOR Pre-Prod GFRC will have scheduled maintenance works outage from 9.00am Wednesday 9 April until 12pm (EST)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Completed - CHG0102344 - Maintenance activities to be performed on the Declared Wholesale Gas Market Systems Pre-Production.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Declared Wholesale Gas Market (DWGM)
Change Title: Maintenance activities to be performed on the Declared Wholesale Gas Market Systems Pre-Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Completed - CHG0102325 - Maintenance activities to be performed on Gas Short Term Trading Market Systems Pre-Production.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Short Term Trading Market (STTM)
Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Completed - CHG0102489 - Pre-Prod eMDM Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
[EventId:202504221500_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 22 April 2025 15:00
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 22 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 22 April 2025.
Refer to market notice: 126682
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1500 hrs on 22 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504221405_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 22 April 2025 14:05
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 22 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 22 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1405 hrs on 22 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202504221230_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 22 April 2025 12:30
Issued by Australian Energy Market Operator Ltd at 1230 hrs on 22 April 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 22 April 2025.
Refer to market notice: 126667
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1230 hrs on 22 April 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202504221035_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 22 April 2025 10:35
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 22 April 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 22 April 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1035 hrs on 22 April 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV
Cancellation time: 21/04/2025 22:09
Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Refer AEMO Electricity Market Notice 126665
Auto-generated on behalf of Manager NEM Real Time Operations