Filter by category
Filter by Date
CHG0100546 - Production eMDM February Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management
Change Title: Production eMDM February Maintenance Release
Change Start Date & Time: 23/02/2025 10:00:00
Change End Date & Time: 23/02/2025 17:00:00
Outage Start Date & Time: 23/02/2025 10:00:00
Outage End Date & Time: 23/02/2025 14:00:00
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Planned System Maintenance - Declared Wholesale Gas Market (DWGM)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Declared Wholesale Gas Market
Change Title: Planned System Maintenance - Declared Wholesale Gas Market (DWGM)
Change Start Date & Time: 18/02/2025 09:00:00
Change End Date & Time: 18/02/2025 21:00:00
Outage Start Date & Time: 18/02/2025 18:30:00
Outage End Date & Time: 18/02/2025 20:30:00
Environment: Production
Participant Impact and Requirements: DWGM market system (Webexchanger and MIBB) outage due to planned maintenance.
The following impacts are expected during the maintenance activities:
- All access to the Declared Wholesale Gas Market Production Systems will be unavailable.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Cancellation of Forecast Minimum System Load (MSL) MSL1 event in the Vic Region on 16/02/2025
Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 13/02/2025.
Refer to Market Notice 124560 for MSL1.
AEMO Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025
Update to Market Notice 124467 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2115 MW
o MSL2 - 1615 MW
o MSL3 - 1115 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1230 hrs to 1430 hrs 16/02/2025. Minimum regional demand is forecast to be 2012 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025
Update to Market Notice 124437 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2115 MW
o MSL2 - 1615 MW
o MSL3 - 1115 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1200 hrs to 1500 hrs 16/02/2025. Minimum regional demand is forecast to be 1873 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
CHG0100111 | Completed | Pre-Production | Pre-Prod eMDM February Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM February Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NON-CONFORMANCE Region NSW1 Tuesday, 11 February 2025
NON-CONFORMANCE NSW1 Region Tuesday, 11 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 11/02/2025 13:55 to 11/02/2025 14:00
Amount: -11 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2060 MW
o MSL2 - 1560 MW
o MSL3 - 1060 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1430 hrs 16/02/2025. Minimum regional demand is forecast to be 1838 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
NON-CONFORMANCE Region NSW1 Monday, 10 February 2025
NON-CONFORMANCE NSW1 Region Monday, 10 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GULLRWF2
Duration: 10/02/2025 11:15 to 10/02/2025 14:10
Amount: 13 MW
Constraint: NC-N_GULLRWF2
Auto-generated on behalf of Manager NEM Real Time Operations