Filter by category
Filter by Date
[EventId:202412271905_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 27 December 2024 19:05
Issued by Australian Energy Market Operator Ltd at 1905 hrs on 27 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 December 2024.
Refer to market notice: 122533
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1905 hrs on 27 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412271830_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 27 December 2024 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 27 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 27 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1830 hrs on 27 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Duration: 27/12/2024 17:28 until further notice
Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Cancellation time: 27/12/2024 16:29
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 122523
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202412271510_confirmed] Prices for interval 27-Dec-2024 15:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 27 December 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Dec-2024 15:10.
In accordance with Market Notice 122518 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412271530_confirmed] Prices for interval 27-Dec-2024 15:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 27 December 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Dec-2024 15:30.
In accordance with Market Notice 122522 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412271525_confirmed] Prices for interval 27-Dec-2024 15:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 27 December 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Dec-2024 15:25.
In accordance with Market Notice 122521 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412271520_confirmed] Prices for interval 27-Dec-2024 15:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 27 December 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Dec-2024 15:20.
In accordance with Market Notice 122520 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412271515_confirmed] Prices for interval 27-Dec-2024 15:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 27 December 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Dec-2024 15:15.
In accordance with Market Notice 122519 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.