Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025
Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025
At 0641 hrs 12/03/2025 there was an unplanned outage of Waterloo - Hummocks 132kV Line.
The following constraint set(s) invoked at 0650 hrs 12/03/2025
S-HUWT
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025
Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025
At 0917 hrs 11/03/2025 there was an unplanned outage of Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line.
The following constraint set(s) invoked at 0925 hrs 11/03/2025
S-KNPW and S-PWSE.
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Non-credible contingency event - SA region - 11/03/2025
Non-credible contingency event - SA region - 11/03/2025
At 0917 hrs the Penola West - South East 132 kV line and the Kincraig - Penola West 132 kV line tripped.
AEMO did not instruct load shedding.
Approximately 3 MW of electrical load has been disconnected.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 125446 is cancelled at 2015 hrs 09/03/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1930 hrs 09/03/2025 to 2030 hrs 09/03/2025.
The forecast capacity reserve requirement is 650 MW.
The minimum capacity reserve available is 600 MW.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 08/03/2025
Cancellation - AEMO Intervention Event - SA region 08/03/2025
Refer to Market Notice 125396
The AEMO Intervention Event and all associated directions are cancelled from 1330 hrs on 09/03/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125398
Direction is cancelled from: 1330 hrs 09/03/2025
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 125424 is cancelled at 1200 hrs 09/03/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 09/03/2025 to 1930 hrs 09/03/2025.
The forecast capacity reserve requirement is 650 MW.
The minimum capacity reserve available is 617 MW.
Manager NEM Real Time Operations