Filter by category
Filter by Date
[EventId:202412122120_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 12 December 2024 21:20
Issued by Australian Energy Market Operator Ltd at 2120 hrs on 12 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 December 2024.
Refer to market notice: 121798
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2120 hrs on 12 December 2024.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121800 is cancelled at 1945hrs 12/12/2024
No LOR condition is currently forecast in the PDPASA period
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121782 has been updated at 1630 hrs to the following:
[1.] From 1600 hrs 13/12/2024 to 1800 hrs 13/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 926 MW.
[2.] From 1900 hrs 13/12/2024 to 1930 hrs 13/12/2024.
The forecast capacity reserve requirement is 1500 MW.
The minimum capacity reserve available is 1327 MW.
Manager NEM Real Time Operations
[EventId:202412121625_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 12 December 2024 16:25
Issued by Australian Energy Market Operator Ltd at 1625 hrs on 12 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1625 hrs on 12 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 16/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:
From 1730 hrs to 1830 hrs 16/12/2024.
The forecast capacity reserve requirement is 238 MW.
The minimum capacity reserve available is 185 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 16/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following period:
From 1530 hrs to 1630 hrs 16/12/2024.
The forecast capacity reserve requirement is 1156 MW.
The minimum capacity reserve available is 694 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 17/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1800 hrs to 1900 hrs 17/12/2024.
The forecast capacity reserve requirement is 990 MW.
The minimum capacity reserve available is 836 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1700 hrs to 1830 hrs 15/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1062 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 1200 hrs to 1430 hrs 17/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 2000 hrs to 2200 hrs 17/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 710 MW.
AEMO Operations