Update - Non-credible contingency event - QLD region - 16/04/2025
Update - Non-credible contingency event - QLD region - 16/04/2025
Refer AEMO Electricity Market Notice 126579
At 1231 hrs the Greenbank - Molendinar 8825 275kV line was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 16/04/2025
Refer market notice: 126577
Non-credible contingency event - QLD region - 16/04/2025
At 2110 hrs the Greenbank - Molendinar 8825 275kV line tripped at the Molendinar end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 14/04/2025
Cancellation of Actual (LOR1) condition in the NSW region - 14/04/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.126559 is cancelled at 1811 hrs 14/04/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/04/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/04/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1588 MW
The minimum capacity reserve available is 1553 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 10/04/2025
Cancellation of Actual (LOR1) condition in the NSW region - 10/04/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.126487 is cancelled at 1910 hrs 10/04/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/04/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 10/04/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1585 MW
The minimum capacity reserve available is 1337 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 09/04/2025
Cancellation of Actual (LOR1) condition in the NSW region - 09/04/2025
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.126458 is cancelled at 1845 hrs 09/04/2025.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/04/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 09/04/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1549 MW
The minimum capacity reserve available is 1164 MW
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 04/04/2025
Update - Non-credible contingency event - QLD region - 04/04/2025
Refer AEMO Electricity Market Notice 126262
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will cancel the reclassification of this event as a credible contingency event.
Manager NEM Real Time Operations