Market Notices

122344MINIMUM SYSTEM LOAD21/12/2024 08:57:33 AM

Cancellation of Forecast Minimum System Load (MSL) MSL1 event in the VIC Region on 21/12/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Forecast Minimum System Load (MSL) MSL1 event in the VIC Region on 21/12/2024.

Cancellation - Forecast MSL1- VIC Region at 0900 hrs 21/12/2024.

Refer to Market Notice 122109 for MSL1.

Manager NEM Real Time Operations
     
122341MINIMUM SYSTEM LOAD21/12/2024 03:08:02 AM

Forecast Minimum System Load MSL2 condition in the VIC Region on 22/12/2024

AEMO ELECTRICITY MARKET NOTICE
Forecast Minimum System Load MSL2 condition in the VIC Region on 22/12/2024

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 22/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1825 MW
- MSL2 - 1325 MW
- MSL3 - 825 MW

The regional demand is forecast to be below the MSL2 threshold for the following period[s]:
- From 1200 hrs 22/12/2024 to 1330 hrs 22/12/2024. Minimum regional demand is forecast to be 1276 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .


Manager NEM Real Time Operations
     
122340MARKET INTERVENTION21/12/2024 03:54:16 AM

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 122297

Direction is cancelled from: 0400 hrs 21/12/2024

Manager NEM Real Time Operations
     
122318INTER-REGIONAL TRANSFER20/12/2024 03:28:59 PM

Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South East No.61 Capacitor 275kV - SA region - 20/12/2024

At 1445 hrs 20/12/2024 there was an unplanned outage of South East No.61 Capacitor 275kV.

The following constraint set(s) invoked at 1445 hrs 20/12/2024
S-SE_1CP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
122317INTER-REGIONAL TRANSFER20/12/2024 03:16:23 PM

Update Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Lismore SVC 132kV - NSW region - 20/12/2024

At 1300 hrs 20/12/2024 there was a short notice outage of Lismore SVC 132kV.

The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
122312MARKET INTERVENTION20/12/2024 02:45:17 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122279


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1445 hrs 20/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0400 hrs 21/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 22/12/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
122311MARKET INTERVENTION20/12/2024 02:43:35 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122277

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 22/12/2024.

The direction update is issued at 1445 hrs 20/12/2024.

Manager NEM Real Time Operations
     
122310INTER-REGIONAL TRANSFER20/12/2024 01:01:43 PM

Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - [outage element] - NSW region - 20/12/2024

At 1300 hrs 20/12/2024 there was a short notice outage of [outage element].

The following constraint set(s) invoked at 1300 hrs 20/12/2024
N-LS_VC1

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
122308MINIMUM SYSTEM LOAD20/12/2024 12:58:35 PM

Cancellation of Forecast Minimum System Load MSL2 event in the VIC Region on 22/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast MSL2 - VIC Region at 1200 hrs 20/12/2024.

Refer to Market Notice 122305 for MSL2.

AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm