123186RESERVE NOTICE13/01/2025 08:44:43 PM

Cancellation of Actual (LOR1) condition in the NSW region - 13/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 13/01/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.123180 is cancelled at 2045 hrs 13/01/2025.

Manager NEM Real Time Operations
     
123180RESERVE NOTICE13/01/2025 06:20:05 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025

Refer market notice: 123171

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1365 MW.
The minimum capacity reserve available is 966 MW.

Manager NEM Real Time Operations
     
123171RESERVE NOTICE13/01/2025 04:58:29 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1700 hrs

The capacity reserve requirement is 1390 MW
The minimum capacity reserve available is 861 MW

Manager NEM Real Time Operations
     
123167RESERVE NOTICE13/01/2025 04:33:47 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123157 has been updated at 1630 hrs to the following:


[1.] From 1630 hrs 13/01/2025 to 1700 hrs 13/01/2025.
The forecast capacity reserve requirement is 1372 MW.
The minimum capacity reserve available is 1061 MW.

[2.] From 1900 hrs 13/01/2025 to 2000 hrs 13/01/2025.
The forecast capacity reserve requirement is 1603 MW.
The minimum capacity reserve available is 1214 MW.


Manager NEM Real Time Operations
     
123160MARKET INTERVENTION13/01/2025 03:11:55 PM

Cancellation - AEMO Intervention Event - SA region 12/01/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 12/01/2025

Refer to Market Notice 123112

The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 13/01/2025.


Manager NEM Real Time Operations
     
123159MARKET INTERVENTION13/01/2025 03:10:02 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 123113

Direction is cancelled from: 1500 hrs 13/01/2025

Manager NEM Real Time Operations
     
123158RESERVE NOTICE13/01/2025 02:37:43 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123108 has been updated at 1400 hrs 13/01/2025 to the following:

From 1700 hrs to 1900 hrs 15/01/2025.
The forecast capacity reserve requirement is 1804 MW.
The minimum capacity reserve available is 1640 MW.

AEMO Operations
     
123157RESERVE NOTICE13/01/2025 02:20:58 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/01/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 123154 has been updated at 1400 hrs to the following:


[1.] From 1630 hrs 13/01/2025 to 2000 hrs 13/01/2025.
The forecast capacity reserve requirement is 1602 MW.
The minimum capacity reserve available is 1056 MW.


Manager NEM Real Time Operations
     
123155MARKET INTERVENTION13/01/2025 12:22:54 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 14/01/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.