Market Notices

120933PRICES SUBJECT TO REVIEW25/11/2024 04:25:10 PM

[EventId:202411251630_review] Prices for interval 25-Nov-2024 16:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1625 hrs on 25 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Nov-2024 16:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120932PRICES SUBJECT TO REVIEW25/11/2024 04:20:11 PM

[EventId:202411251625_review] Prices for interval 25-Nov-2024 16:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1620 hrs on 25 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Nov-2024 16:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120931PRICES SUBJECT TO REVIEW25/11/2024 04:15:16 PM

[EventId:202411251620_review] Prices for interval 25-Nov-2024 16:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 25 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Nov-2024 16:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120930PRICES SUBJECT TO REVIEW25/11/2024 04:10:10 PM

[EventId:202411251615_review] Prices for interval 25-Nov-2024 16:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1610 hrs on 25 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Nov-2024 16:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120929PRICES SUBJECT TO REVIEW25/11/2024 04:05:25 PM

[EventId:202411251610_review] Prices for interval 25-Nov-2024 16:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 25 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Nov-2024 16:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120928PRICES SUBJECT TO REVIEW25/11/2024 04:00:15 PM

[EventId:202411251605_review] Prices for interval 25-Nov-2024 16:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1600 hrs on 25 November 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 25-Nov-2024 16:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
120919INTER-REGIONAL TRANSFER25/11/2024 02:03:31 PM

Inter-Regional Transfer limit variation - Murraylink

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink

There has been an unplanned outage of Murraylink.

The following constraint set was invoked at 1405 hrs 25/11/2024

I-ML_ZERO

The constraint set contains the following interconnector on the left hand side.

V-S-MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
120836INTER-REGIONAL TRANSFER22/11/2024 07:32:00 PM

Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Directlink - NSW region - 22/11/2024

At 1911 hrs 22/11/2024 there was an unplanned outage of the No.2 leg of Directlink.

The following constraint set(s) invoked at 1920 hrs 22/11/2024
N-X_MBTE_2

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
120831INTER-REGIONAL TRANSFER22/11/2024 05:29:01 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 2 Leg of Directlink .

The following constraint set was invoked at 1720 hrs 22/11/2024

N-X_MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm