Market Notices

123327RECLASSIFY CONTINGENCY15/01/2025 04:59:17 PM

Cancellation of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV

Cancellation time: 15/01/2025 16:59

Constraint set(s) revoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 123267

Auto-generated on behalf of Manager NEM Real Time Operations
     
123326PRICES SUBJECT TO REVIEW15/01/2025 04:55:28 PM

[EventId:202501151700_review] Prices for interval 15-Jan-2025 17:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1655 hrs on 15 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 17:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123325RECLASSIFY CONTINGENCY15/01/2025 04:51:16 PM

Reclassification of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line

Duration: 15/01/2025 16:51 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
123324PRICES SUBJECT TO REVIEW15/01/2025 04:50:21 PM

[EventId:202501151655_review] Prices for interval 15-Jan-2025 16:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1650 hrs on 15 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123322PRICES SUBJECT TO REVIEW15/01/2025 04:45:24 PM

[EventId:202501151650_review] Prices for interval 15-Jan-2025 16:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123321PRICES SUBJECT TO REVIEW15/01/2025 04:42:04 PM

[EventId:202501151645_review] Prices for interval 15-Jan-2025 16:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1640 hrs on 15 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123320PRICES SUBJECT TO REVIEW15/01/2025 04:39:31 PM

[EventId:202501151640_review] Prices for interval 15-Jan-2025 16:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1635 hrs on 15 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123318PRICES UNCHANGED15/01/2025 04:36:59 PM

[EventId:202501151610_confirmed] Prices for interval 15-Jan-2025 16:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 15 January 2025

PRICES ARE NOW CONFIRMED for trading interval 15-Jan-2025 16:10.

In accordance with Market Notice 123306 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
123317PRICES SUBJECT TO REVIEW15/01/2025 04:35:46 PM

[EventId:202501151635_review] Prices for interval 15-Jan-2025 16:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 15 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 15-Jan-2025 16:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     