[EventId:202412061430_confirmed] Prices for interval 06-Dec-2024 14:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 6 December 2024
PRICES ARE NOW CONFIRMED for trading interval 06-Dec-2024 14:30.
In accordance with Market Notice 121506 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412061450_confirmed] Prices for interval 06-Dec-2024 14:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 6 December 2024
PRICES ARE NOW CONFIRMED for trading interval 06-Dec-2024 14:50.
In accordance with Market Notice 121513 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412061445_confirmed] Prices for interval 06-Dec-2024 14:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 6 December 2024
PRICES ARE NOW CONFIRMED for trading interval 06-Dec-2024 14:45.
In accordance with Market Notice 121512 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412061440_confirmed] Prices for interval 06-Dec-2024 14:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 6 December 2024
PRICES ARE NOW CONFIRMED for trading interval 06-Dec-2024 14:40.
In accordance with Market Notice 121509 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412061435_confirmed] Prices for interval 06-Dec-2024 14:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 6 December 2024
PRICES ARE NOW CONFIRMED for trading interval 06-Dec-2024 14:35.
In accordance with Market Notice 121507 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412061425_confirmed] Prices for interval 06-Dec-2024 14:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 6 December 2024
PRICES ARE NOW CONFIRMED for trading interval 06-Dec-2024 14:25.
In accordance with Market Notice 121505 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Forecast Minimum System Load (MSL1) condition in the VIC region on 08/12/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 08/12/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1590 MW
o MSL2 - 1090 MW
o MSL3 - 590 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 1200 hrs 08/12/2024 to 1330 hrs 08/12/2024. Minimum regional demand is forecast to be 1496 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC1
Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV
Duration: 06/12/2024 10:46 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Duration: 06/12/2024 10:09 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations