PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/03/2025
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 125671 has been updated to the following:
From 1630 hrs 16/03/2025 to 1930 hrs 16/03/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 880 MW.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Ross - Tully South - Woree No.8905 275 kV line line and Cardwell - Tully No.7389 132kV line line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Ross - Tully South - Woree No.8905 275 kV line and Cardwell - Tully No.7389 132kV line
Cancellation time: 15/03/2025 17:33
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 125672
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202503151620_confirmed] Prices for interval 15-Mar-2025 16:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:20.
In accordance with Market Notice 125673 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503151645_confirmed] Prices for interval 15-Mar-2025 16:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:45.
In accordance with Market Notice 125681 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503151640_confirmed] Prices for interval 15-Mar-2025 16:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:40.
In accordance with Market Notice 125679 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503151635_confirmed] Prices for interval 15-Mar-2025 16:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:35.
In accordance with Market Notice 125677 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503151630_confirmed] Prices for interval 15-Mar-2025 16:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:30.
In accordance with Market Notice 125676 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202503151625_confirmed] Prices for interval 15-Mar-2025 16:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1645 hrs on 15 March 2025
PRICES ARE NOW CONFIRMED for trading interval 15-Mar-2025 16:25.
In accordance with Market Notice 125674 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/03/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 15/03/2025 to 1830 hrs 15/03/2025.
The forecast capacity reserve requirement is 1663 MW.
The minimum capacity reserve available is 1546 MW.
Manager NEM Real Time Operations