Inital - CHG0101876 - Pre-Prod eMDM Hotfix Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management_PreProd
Change Title: Pre-Prod eMDM Hotfix Maintenance Release
Change Start Date & Time: 12/03/2025 13:00:00
Change End Date & Time: 12/03/2025 17:00:00
Outage Start Date & Time: 12/03/2025 13:00:00
Outage End Date & Time: 12/03/2025 17:00:00
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025
Inter-regional transfer limit variation - Waterloo - Hummocks 132kV Line - SA region - 12/03/2025
At 0641 hrs 12/03/2025 there was an unplanned outage of Waterloo - Hummocks 132kV Line.
The following constraint set(s) invoked at 0650 hrs 12/03/2025
S-HUWT
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inital - CHG0101808 - Pre-production EMMS database Maintainence activity
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Data Store
Change Title: Pre-production EMMS database Maintainence activity
Change Start Date & Time: 11/03/2025 01:00:00
Change End Date & Time: 19/03/2025 17:00:00
Outage Start Date & Time: 13/03/2025 12:00:00
Outage End Date & Time: 13/03/2025 15:00:00
Environment: Pre-Production
Participant Impact and Requirements: The Electricity Market Management System (EMMS) , Gas Supply Hub (GSH) and FPP Pre-Production environment will be unavailable during the outage window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025
Inter-regional transfer limit variation - Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line - SA region - 11/03/2025
At 0917 hrs 11/03/2025 there was an unplanned outage of Penola West - South East 132 kV line and Kincraig - Penola West 132 kV line.
The following constraint set(s) invoked at 0925 hrs 11/03/2025
S-KNPW and S-PWSE.
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202503110930_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 11 March 2025 09:30
Issued by Australian Energy Market Operator Ltd at 0930 hrs on 11 March 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 March 2025.
Refer to market notice: 125514
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 0930 hrs on 11 March 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202503110830_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 11 March 2025 08:30
Issued by Australian Energy Market Operator Ltd at 0830 hrs on 11 March 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 March 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0830 hrs on 11 March 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 125446 is cancelled at 2015 hrs 09/03/2025.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1930 hrs 09/03/2025 to 2030 hrs 09/03/2025.
The forecast capacity reserve requirement is 650 MW.
The minimum capacity reserve available is 600 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 125424 is cancelled at 1200 hrs 09/03/2025.
Manager NEM Real Time Operations