124893MARKET SYSTEMS19/02/2025 03:01:56 PM

Completed - CHG0101145 - Planned Maintenance to Norwest Internet Router

Change Number: CHG0101145

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet Router

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
124890MARKET INTERVENTION19/02/2025 03:59:06 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 124832

PPCCGT PELICAN POINT at 0400 hrs 20/02/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 21/02/2025.

The direction update is issued at 1600 hrs 19/02/2025.

Manager NEM Real Time Operations
     
124889MARKET INTERVENTION19/02/2025 03:56:26 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 124831

TORRB2 TORRENS ISLAN at 0400 hrs 20/02/2025 to Remain synchronised and follow dispatch targets.

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 21/02/2025.

The direction update is issued at 1600 hrs 19/02/2025.

Manager NEM Real Time Operations
     
124888MARKET SYSTEMS19/02/2025 01:04:49 PM

Inital - CHG0101252 - Retail Pre-Production Data refresh (CATS and EMDM)

Change Number: CHG0101252

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Retail Pre-Production Data refresh (CATS and EMDM)

Change Start Date & Time: 24/02/2025 09:00:00
Change End Date & Time: 28/02/2025 18:00:00
Outage Start Date & Time: 24/02/2025 09:00:00
Outage End Date & Time: 27/02/2025 18:00:00

Environment: Pre-Production
Participant Impact and Requirements: MSATS (preprod) between 24th Feb - 26 Feb COB, CDR (preprod) and CDP (preprod) will be unavailble between 24th Feb to 28th Feb COB

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
124873MARKET SYSTEMS19/02/2025 11:47:12 AM

Inital - CHG0100546 - Production eMDM February Maintenance Release

Change Number: CHG0100546

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: MDM - Meter Data Management
Change Title: Production eMDM February Maintenance Release

Change Start Date & Time: 23/02/2025 10:00:00
Change End Date & Time: 23/02/2025 17:00:00
Outage Start Date & Time: 23/02/2025 10:00:00
Outage End Date & Time: 23/02/2025 14:00:00

Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
     
124854RECLASSIFY CONTINGENCY18/02/2025 05:34:01 PM

Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 18/02/2025 17:33

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 124851

Auto-generated on behalf of Manager NEM Real Time Operations
     
124853RECLASSIFY CONTINGENCY18/02/2025 05:34:01 PM

Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Cancellation time: 18/02/2025 17:33

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 124850

Auto-generated on behalf of Manager NEM Real Time Operations
     
124851RECLASSIFY CONTINGENCY18/02/2025 04:31:30 PM

Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 18/02/2025 16:31 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
124850RECLASSIFY CONTINGENCY18/02/2025 04:31:30 PM

Reclassification of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV

Duration: 18/02/2025 16:31 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     