NON-CONFORMANCE Region QLD1 Thursday, 23 January 2025
NON-CONFORMANCE QLD1 Region Thursday, 23 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 23/01/2025 05:50 to 23/01/2025 06:05
Amount: 38 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation -Inter-regional transfer limit variation - Constraint invocation to manage Power System Security in NSW region - 22/01/2025
Cancellation -Inter-regional transfer limit variation - Constraint invocation to manage Power System Security in NSW region - 22/01/2025
Refer to MN 123588
In order to maintain the power system in a secure operating state in the NSW region (Northern NSW) ,
AEMO has invoked constraint set #N-Q-MNSP1_E from 1720 hrs until 1845 hs 22/01/2025.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation -Lismore No1 SVC - NSW region - 22/01/2025
Inter-regional transfer limit variation - Lismore No1 SVC - NSW region - 22/01/2025
A planned outage of Lismore No1 SVC in the NSW region was scheduled from 0620 hrs 08/01/2025 to 1600 hrs 24/01/2025.
The outage has been completed and Lismore No1 SVC returned to service at 1900 hrs 22/01/2025
Constraint set(s) revoked: N-LS_VC1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Constraint invocation to manage Power System Security in NSW region - 25/01/2025
In order to maintain the power system in a secure operating state in the NSW region (Northern NSW) , AEMO has invoked constraint set #N-Q-MNSP1_E from 1720 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation -Bundy-Buronga (6F) 330 kV line - NSW region - 21/01/2025
Inter-regional transfer limit variation - - NSW region - 21/01/2025
At 1935 hrs 21/01/2025 there was a short notice outage of Bundy-Buronga (6F) 330 kV line
The following constraint set(s) invoked
I-BDBU_ONE
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,VIC1-NSW1,V-SA,T-V-MNSP1
The outage is scheduled to return to service at 1935 hrs 22/01/2025
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 22 January 2025
NON-CONFORMANCE NSW1 Region Wednesday, 22 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 22/01/2025 08:50 to 22/01/2025 09:00
Amount: 18 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Wednesday, 22 January 2025
NON-CONFORMANCE QLD1 Region Wednesday, 22 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 22/01/2025 06:40 to 22/01/2025 06:45
Amount: 16 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 21 January 2025
NON-CONFORMANCE NSW1 Region Tuesday, 21 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TALWA1
Duration: 21/01/2025 18:35 to 21/01/2025 18:40
Amount: 44 MW
Constraint: NC-N_TALWA1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 21 January 2025
NON-CONFORMANCE QLD1 Region Tuesday, 21 January 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 21/01/2025 09:45 to 21/01/2025 13:55
Amount: 36 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations