[EventId:202501241200_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 January 2025 12:00
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 24 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 January 2025.
Refer to market notice: 123654
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1200 hrs on 24 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501241135_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 January 2025 11:35
Issued by Australian Energy Market Operator Ltd at 1135 hrs on 24 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1135 hrs on 24 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501241105_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 24 January 2025 11:05
Issued by Australian Energy Market Operator Ltd at 1105 hrs on 24 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1105 hrs on 24 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501241100_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 24 January 2025 11:00
Issued by Australian Energy Market Operator Ltd at 1100 hrs on 24 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 January 2025.
Refer to market notice: 123647
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1100 hrs on 24 January 2025.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Bundey to Buronga (6F) 330kV line - NSW region - 24/01/2025
Inter-regional transfer limit variation - Bundey to Buronga (6F) 330kV line - NSW region - 24/01/2025
A planned outage of Bundey to Buronga (6F) 330kV line in the NSW region was scheduled from 1931 hrs 21/01/2025 to 1900 hrs 25/01/2025.
The outage has been completed and Bundey to Buronga (6F) 330kV line returned to service at 0900 hrs 24/01/2025
Constraint set(s) revoked: I-BDBU_ONE
Manager NEM Real Time Operations
[EventId:202501240810_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 January 2025 08:10
Issued by Australian Energy Market Operator Ltd at 0810 hrs on 24 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 0810 hrs on 24 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Lismore No.1 132 kV SVC - NSW region - 23/01/2025
Inter-regional transfer limit variation - Lismore No.1 132 kV SVC - NSW region - 23/01/2025
A planned outage of Lismore No.1 132 kV SVC in the NSW region was scheduled from 2200 hrs 22/01/2025 to 1600 hrs 24/01/2025.
The outage has been completed and Lismore No.1 132 kV SVC returned to service at 1631 hrs 23/01/2025
Constraint set(s) revoked: N-LS_VC1
Manager NEM Real Time Operations
[EventId:202501222200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 22 January 2025 22:00
Issued by Australian Energy Market Operator Ltd at 2200 hrs on 22 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2025.
Refer to market notice: 123585
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 2200 hrs on 22 January 2025.
This is an AEMO autogenerated Market Notice.
Cancellation -Inter-regional transfer limit variation - Constraint invocation to manage Power System Security in NSW region - 22/01/2025
Cancellation -Inter-regional transfer limit variation - Constraint invocation to manage Power System Security in NSW region - 22/01/2025
Refer to MN 123588
In order to maintain the power system in a secure operating state in the NSW region (Northern NSW) ,
AEMO has invoked constraint set #N-Q-MNSP1_E from 1720 hrs until 1845 hs 22/01/2025.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Manager NEM Real Time Operations