124279RESERVE NOTICE06/02/2025 06:53:50 PM

Cancellation of Actual (LOR1) condition in the NSW region - 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 06/02/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.124278 is cancelled at 1845 hrs 06/02/2025.

Manager NEM Real Time Operations
     
124278RESERVE NOTICE06/02/2025 06:17:14 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/02/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1370 MW
The minimum capacity reserve available is 1249 MW

Manager NEM Real Time Operations
     
124277RESERVE NOTICE06/02/2025 06:00:26 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1630 hrs 07/02/2025 to 1700 hrs 07/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1296 MW.


Manager NEM Real Time Operations
     
124265RESERVE NOTICE06/02/2025 05:19:16 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:


[1.] From 1730 hrs 06/02/2025 to 1800 hrs 06/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1347 MW.


[2.] From 1630 hrs 07/02/2025 to 1700 hrs 07/02/2025.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1248 MW.


Manager NEM Real Time Operations
     
124260NON-CONFORMANCE06/02/2025 04:15:13 PM

NON-CONFORMANCE Region QLD1 Thursday, 6 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 6 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: KINGASF1
Duration: 06/02/2025 14:55 to 06/02/2025 16:15
Amount: 29 MW
Constraint: NC-Q_KINGASF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
124255MARKET INTERVENTION06/02/2025 03:12:06 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 124253


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1500 hrs 06/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 07/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/02/2025 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
124254MARKET INTERVENTION06/02/2025 03:12:46 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 124253


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1510 hrs 06/02/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0730 hrs 07/02/2025
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/02/2025 / further notice.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
124253MARKET INTERVENTION06/02/2025 03:00:02 PM

Direction - SA region 06/02/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 06/02/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1505 hrs on 06/02/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
124250MARKET INTERVENTION06/02/2025 02:19:47 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 124240

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0730 hrs 06/02/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1500 hrs 06/02/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     