NEM Local Temperature Alerts for SA, VIC from 11 Mar 2025 to 15 Mar 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 14th Mar, 15th Mar
VIC
Latrobe Valley Ap (39+ Deg C): 15th Mar
Mildura Ap (39+ Deg C): 14th Mar, 15th Mar
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
NON-CONFORMANCE Region NSW1 Tuesday, 11 March 2025
NON-CONFORMANCE NSW1 Region Tuesday, 11 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 11/03/2025 11:25 to 11/03/2025 11:55
Amount: -9 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Inital - CHG0101808 - Pre-production EMMS database Maintainence activity
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Data Store
Change Title: Pre-production EMMS database Maintainence activity
Change Start Date & Time: 11/03/2025 01:00:00
Change End Date & Time: 19/03/2025 17:00:00
Outage Start Date & Time: 13/03/2025 12:00:00
Outage End Date & Time: 13/03/2025 15:00:00
Environment: Pre-Production
Participant Impact and Requirements: The Electricity Market Management System (EMMS) , Gas Supply Hub (GSH) and FPP Pre-Production environment will be unavailable during the outage window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities .
Non-credible contingency event - SA region - 11/03/2025
Non-credible contingency event - SA region - 11/03/2025
At 0917 hrs the Penola West - South East 132 kV line and the Kincraig - Penola West 132 kV line tripped.
AEMO did not instruct load shedding.
Approximately 3 MW of electrical load has been disconnected.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 10 March 2025
NON-CONFORMANCE QLD1 Region Monday, 10 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 10/03/2025 13:00 to 10/03/2025 13:05
Amount: -11 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
NEM Local Temperature Alerts for SA, TAS from 10 Mar 2025 to 14 Mar 2025
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Adelaide West Terrace (39+ Deg C): 10th Mar
Port Augusta Ap (39+ Deg C): 10th Mar, 14th Mar
TAS
Launceston Ti Tree Bend (33+ Deg C): 10th Mar
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
Cancellation - AEMO Intervention Event - SA region 08/03/2025
Cancellation - AEMO Intervention Event - SA region 08/03/2025
Refer to Market Notice 125396
The AEMO Intervention Event and all associated directions are cancelled from 1330 hrs on 09/03/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125398
Direction is cancelled from: 1330 hrs 09/03/2025
Manager NEM Real Time Operations
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 125396.
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 08/03/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0400 hrs 09/03/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1330 hrs 09/03/2025.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations