NON-CONFORMANCE Region QLD1 Wednesday, 5 March 2025
NON-CONFORMANCE QLD1 Region Wednesday, 5 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 05/03/2025 17:35 to 05/03/2025 17:45
Amount: -12 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Update - Non-credible contingency event - NSW region - 05/03/2025
Update - Non-credible contingency event - NSW region - 05/03/2025
Refer AEMO Electricity Market Notice 125268
At 1400 hrs the Directlink DC1 was returned to service.
(At 1030 hrs the Ewingsdale-Mullumbimby 9G5 132kV line was returned to service.)
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 5 March 2025
NON-CONFORMANCE NSW1 Region Wednesday, 5 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 05/03/2025 12:00 to 05/03/2025 12:25
Amount: -120 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
Non-credible contingency event - NSW region - 05/03/2025
Non-credible contingency event - NSW region - 05/03/2025
At 1030 hrs the Ewingsdale-Mullumbimby 9G5 132kV line and the Directlink DC1 tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 4 March 2025
NON-CONFORMANCE NSW1 Region Tuesday, 4 March 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 04/03/2025 11:55 to 04/03/2025 12:00
Amount: -33 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 27 February 2025
NON-CONFORMANCE QLD1 Region Thursday, 27 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TARONG#1
Duration: 27/02/2025 21:25 to 27/02/2025 21:35
Amount: -11 MW
Constraint: NC-Q_TARONG#1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Thursday, 27 February 2025
NON-CONFORMANCE QLD1 Region Thursday, 27 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WDBESS1
Duration: 27/02/2025 18:35 to 27/02/2025 18:50
Amount: -55 MW
Constraint: NC-Q_WDBESS1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Thursday, 27 February 2025
NON-CONFORMANCE NSW1 Region Thursday, 27 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 27/02/2025 08:45 to 27/02/2025 08:55
Amount: -7 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 26 February 2025
NON-CONFORMANCE NSW1 Region Wednesday, 26 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BERYLSF1
Duration: 26/02/2025 12:15 to 26/02/2025 12:40
Amount: 76 MW
Constraint: NC-N_BERYLSF1
Auto-generated on behalf of Manager NEM Real Time Operations