124440MARKET INTERVENTION10/02/2025 03:30:19 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 124394

The PPCCGT PELICAN POINT direction is now expected to stay in place until 1030 hrs 11/02/2025.

The direction update is issued at 1530 hrs 10/02/2025.

Manager NEM Real Time Operations
     
124437MINIMUM SYSTEM LOAD10/02/2025 03:30:40 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2060 MW
o MSL2 - 1560 MW
o MSL3 - 1060 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1430 hrs 16/02/2025. Minimum regional demand is forecast to be 1838 MW at 1330 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .


AEMO Operations
     
124436NON-CONFORMANCE10/02/2025 02:10:15 PM

NON-CONFORMANCE Region NSW1 Monday, 10 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 10 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GULLRWF2
Duration: 10/02/2025 11:15 to 10/02/2025 14:10
Amount: 13 MW
Constraint: NC-N_GULLRWF2

Auto-generated on behalf of Manager NEM Real Time Operations
     
124414MARKET INTERVENTION10/02/2025 08:10:06 AM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 124396

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1730 hrs 10/02/2025.

The direction update is issued at 0810 hrs 10/02/2025.

Manager NEM Real Time Operations
     
124396MARKET INTERVENTION09/02/2025 04:02:45 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 124357

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 11/02/2025.

The direction update is issued at 1600 hrs 09/02/2025.

Manager NEM Real Time Operations
     
124394MARKET INTERVENTION09/02/2025 04:01:02 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 124358

The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 11/02/2025.

The direction update is issued at 1600 hrs 09/02/2025.

Manager NEM Real Time Operations
     
124358MARKET INTERVENTION08/02/2025 02:15:45 PM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 124254

The PPCCGT PELICAN POINT direction is now expected to stay in place until 0400 hrs 10/02/2025.

The direction update is issued at 1415 hrs 08/02/2025.

Manager NEM Real Time Operations
     
124357MARKET INTERVENTION08/02/2025 02:15:24 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 124255

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 10/02/2025.

The direction update is issued at 1415 hrs 08/02/2025.

Manager NEM Real Time Operations
     
124339NON-CONFORMANCE08/02/2025 08:05:22 AM

NON-CONFORMANCE Region VIC1 Saturday, 8 February 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Saturday, 8 February 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LYA2
Duration: 08/02/2025 07:55 to 08/02/2025 08:05
Amount: -39 MW
Constraint: NC-V_LYA2

Auto-generated on behalf of Manager NEM Real Time Operations
     