Market Notices

123182NON-CONFORMANCE13/01/2025 07:20:16 PM

NON-CONFORMANCE Region NSW1 Monday, 13 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 13 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 13/01/2025 19:10 to 13/01/2025 19:20
Amount: -8 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
123180RESERVE NOTICE13/01/2025 06:20:05 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025

Refer market notice: 123171

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1800 hrs.

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1365 MW.
The minimum capacity reserve available is 966 MW.

Manager NEM Real Time Operations
     
123171RESERVE NOTICE13/01/2025 04:58:29 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 13/01/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.
The Actual LOR1 condition is forecast to exist until 1700 hrs

The capacity reserve requirement is 1390 MW
The minimum capacity reserve available is 861 MW

Manager NEM Real Time Operations
     
123156NON-CONFORMANCE13/01/2025 01:50:19 PM

NON-CONFORMANCE Region QLD1 Monday, 13 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 13 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 13/01/2025 11:35 to 13/01/2025 13:50
Amount: 57 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
122992NON-CONFORMANCE10/01/2025 09:50:20 AM

NON-CONFORMANCE Region NSW1 Friday, 10 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 10 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: TALWA1
Duration: 10/01/2025 09:45 to 10/01/2025 09:50
Amount: -24 MW
Constraint: NC-N_TALWA1

Auto-generated on behalf of Manager NEM Real Time Operations
     
122991NON-CONFORMANCE10/01/2025 05:25:13 AM

NON-CONFORMANCE Region NSW1 Friday, 10 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 10 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 10/01/2025 05:15 to 10/01/2025 05:25
Amount: -47 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
     
122982NON-CONFORMANCE09/01/2025 08:30:19 AM

NON-CONFORMANCE Region QLD1 Thursday, 9 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 9 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: KINGASF1
Duration: 09/01/2025 08:15 to 09/01/2025 08:30
Amount: 35 MW
Constraint: NC-Q_KINGASF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
122824NON-CONFORMANCE03/01/2025 10:15:14 PM

NON-CONFORMANCE Region QLD1 Friday, 3 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 3 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 03/01/2025 21:35 to 03/01/2025 22:15
Amount: -57 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
122647NON-CONFORMANCE01/01/2025 12:45:12 AM

NON-CONFORMANCE Region QLD1 Wednesday, 1 January 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 1 January 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 01/01/2025 00:00 to 01/01/2025 00:45
Amount: 40 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm