120909NON-CONFORMANCE25/11/2024 12:30:19 PM

NON-CONFORMANCE Region NSW1 Monday, 25 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 25 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 25/11/2024 11:55 to 25/11/2024 12:30
Amount: -142 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120897RECALL GEN CAPACITY25/11/2024 08:40:06 AM

Request for Generator Recall Information for the period 27/11/2024 for Region QLD

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 120895.

Please provide Generator Recall Information for the period from 27/11/2024, by 1500 hrs on 25/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
120896RECALL GEN CAPACITY25/11/2024 08:38:28 AM

Request for Generator Recall Information for the period 27/11/2024 for Region NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 120894, and 120892.

Please provide Generator Recall Information for the period from 27/11/2024, by 1500 hrs on 25/11/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf


AEMO Operations
     
120891NON-CONFORMANCE24/11/2024 07:45:13 PM

NON-CONFORMANCE Region QLD1 Sunday, 24 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 24 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 24/11/2024 19:00 to 24/11/2024 19:45
Amount: 13 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120877NON-CONFORMANCE24/11/2024 10:35:23 AM

NON-CONFORMANCE Region QLD1 Sunday, 24 November 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Sunday, 24 November 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WHITSF1
Duration: 24/11/2024 09:25 to 24/11/2024 10:35
Amount: 53 MW
Constraint: NC-Q_WHITSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
120809PRICES UNCHANGED22/11/2024 11:50:28 AM

[EventId:202411221125_confirmed] Prices for interval 22-Nov-2024 11:25 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1145 hrs on 22 November 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:25.

In accordance with Market Notice 120798 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120808PRICES UNCHANGED22/11/2024 11:49:12 AM

[EventId:202411221145_confirmed] Prices for interval 22-Nov-2024 11:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1145 hrs on 22 November 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:45.

In accordance with Market Notice 120803 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120807PRICES UNCHANGED22/11/2024 11:47:57 AM

[EventId:202411221140_confirmed] Prices for interval 22-Nov-2024 11:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1145 hrs on 22 November 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:40.

In accordance with Market Notice 120802 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
120806PRICES UNCHANGED22/11/2024 11:51:40 AM

[EventId:202411221135_confirmed] Prices for interval 22-Nov-2024 11:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1145 hrs on 22 November 2024

PRICES ARE NOW CONFIRMED for trading interval 22-Nov-2024 11:35.

In accordance with Market Notice 120801 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.