[EventId:202502101600_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 February 2025 16:00
Issued by Australian Energy Market Operator Ltd at 1600 hrs on 10 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Refer to market notice: 124442
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1600 hrs on 10 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502101505_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 February 2025 15:05
Issued by Australian Energy Market Operator Ltd at 1505 hrs on 10 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1505 hrs on 10 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Forecast Minimum System Load (MSL1) condition in the VIC region on 16/02/2025
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 16/02/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 2060 MW
o MSL2 - 1560 MW
o MSL3 - 1060 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1430 hrs 16/02/2025. Minimum regional demand is forecast to be 1838 MW at 1330 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
NON-CONFORMANCE Region NSW1 Monday, 10 February 2025
NON-CONFORMANCE NSW1 Region Monday, 10 February 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GULLRWF2
Duration: 10/02/2025 11:15 to 10/02/2025 14:10
Amount: 13 MW
Constraint: NC-N_GULLRWF2
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202502101300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 February 2025 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 10 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Refer to market notice: 124421
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 10 February 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202502101220_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 February 2025 12:20
Issued by Australian Energy Market Operator Ltd at 1220 hrs on 10 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1220 hrs on 10 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202502101200_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 10 February 2025 12:00
Issued by Australian Energy Market Operator Ltd at 1200 hrs on 10 February 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Refer to market notice: 124415
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1200 hrs on 10 February 2025.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025
Inter-regional transfer limit variation - Ingleburn - Wallerawang (77) 330 kV line - NSW region - 10/02/2025
At 0945 hrs 10/02/2025 there was an unplanned outage of Ingleburn - Wallerawang (77) 330 kV line.
The following constraint set(s) invoked at 0955 hrs 10/02/2025
N-X_AVMA_SSWW
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202502101000_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 10 February 2025 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 10 February 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 10 February 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1000 hrs on 10 February 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.